The PRINCE2 Practitioner exam has a reputation for tripping up even experienced candidates. Working through 266 realistic practice questions from ActualCollection exposes your weak spots before exam day does.
PRINCE2 PRINCE2Practitioner Exam Overview:
| Certification Vendor: | AXELOS / PeopleCert |
|---|---|
| Exam Name: | PRINCE2 Practitioner Certification Exam (7th Edition) |
| Exam Number: | PRINCE2Practitioner |
| Certificate Validity Period: | 3 years |
| Passing Score: | 60% (42/70) |
| Exam Format: | Scenario-based objective testing, Multiple choice, Open book (official PRINCE2 manual only) |
| Related Certifications: | PRINCE2 Foundation |
| Exam Price: | USD 400–520 / GBP 470–520 |
| Available Languages: | Polish, Portuguese, German, English, Spanish, French |
| Exam Duration: | 150 minutes |
| Real Exam Qty: | 70 |
| Recommended Training: | Official PRINCE2 Training |
| Exam Registration: | PeopleCert Official Registration |
| Sample Questions: | ![]() |
| Exam Way: | Online remote proctored or onsite test center |
| Pre Condition: | Hold valid PRINCE2 Foundation certification, or equivalent: PMP, CAPM, IPMA Levels A/B/C/D |
| Official Syllabus URL: | https://www.axelos.com/certifications/prince2/prince2-practitioner |
PRINCE2 PRINCE2Practitioner Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: PRINCE2 Processes | 30% | - Directing a Project - Closing a Project - Initiating a Project - Controlling a Stage - Starting up a Project - Managing Product Delivery - Managing a Stage Boundary |
| Topic 2: PRINCE2 Principles | 20% | - Learn from experience - Tailor to suit the project environment - Focus on products - Manage by stages - Defined roles and responsibilities - Continued business justification - Manage by exception |
| Topic 3: Tailoring PRINCE2 | 10% | - Tailoring principles, themes and processes - Adapting to project size, complexity and context |
| Topic 4: PRINCE2 Themes | 40% | - Risk - Change - Quality - Plans - Organization - Progress - Business Case |
Answers Every PRINCE2Practitioner Candidate Should Read First
The PRINCE2 Practitioner exam is the official AXELOS / PeopleCert test registered under exam code PRINCE2Practitioner. Passing it earns you the PRINCE2 Practitioner certification, a credential at the Professional level. It is also linked to the related certification: PRINCE2 Foundation. AXELOS / PeopleCert exams are valued because they test job-ready skills, so a passing score here carries real weight on a resume.
The PRINCE2 Practitioner exam includes 70 questions to be completed within 150 minutes. Do the pacing math before exam day: with that many items on the clock, you need a steady rhythm and the discipline to flag a hard question and move on instead of stalling. Two or three full timed sessions with the ActualCollection test engine will show you exactly what that pace feels like, so time pressure stops being a factor on the real day.
To pass the PRINCE2 Practitioner exam you need 60% (42/70), and the official registration fee is USD 400–520 / GBP 470–520. A retake is not discounted: a failed attempt means paying the full USD 400–520 / GBP 470–520 again, so treat your first sitting as the expensive one. A sensible rule is to book your seat only after you are scoring comfortably above the passing mark on the ActualCollection practice tests, not just squeaking past it once.
Hold valid PRINCE2 Foundation certification, or equivalent: PMP, CAPM, IPMA Levels A/B/C/D
Eligibility rules do change from time to time, so confirm the current requirements before you register on the official exam page.
Registration for the PRINCE2 Practitioner exam goes through the official channels below.
As for the delivery format, the exam is taken Online remote proctored or onsite test center.
AXELOS / PeopleCert points candidates toward the following training options for PRINCE2 Practitioner.
Course work builds the foundation; question practice makes it stick. The 266 practice questions in the ActualCollection PRINCE2Practitioner package let you rehearse each topic under exam-style pressure before the real thing.
Yes. ActualCollection offers a free PDF demo of the PRINCE2 Practitioner material so you can judge the question quality and format before spending anything. After purchase, your license includes 365 days of free updates, and if you want to keep receiving updates after that period, renewals are available at a 50% discount.
If you take the PRINCE2 Practitioner exam within 60 days of your purchase and do not pass, ActualCollection backs you with a 100% money-back guarantee. The claim must match the exam your product covers: attempts taken within 3 days of purchase are not eligible (that is too little preparation time), and neither are downloaded-but-unused products, free materials, or expired orders. The candidate name must match the payer name, and you need to submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Prefer not to refund? You can swap instead and receive two other exam products of equal value for free while keeping the update service on your original purchase.
Delivery itself is instant: your files are downloadable right away and emailed to you within one minute of payment. If nothing arrives within 2 hours, contact customer service. There is no limit on how many computers you may install the software on.
The official PRINCE2 Practitioner syllabus is organized into 4 domains. Key areas include Tailoring PRINCE2 (10%), PRINCE2 Themes (40%), and PRINCE2 Principles (20%). The complete, up-to-date topic list appears in the exam topics section above; work through it line by line and flag anything you cannot yet explain in your own words.
PRINCE2 Practitioner Sample Questions:
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
* 20% discount for all repeat customers - not cost-effective and very short term
* A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
* A series of television and press advertisements was too expensive
* A direct mail shot to all customers - benefit would be short term
* Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.
Which 2 statements should be recorded under the Expected benefits heading?
- A. The Marketing department want a very high quality, glossy product as they believe this will be more appealing to customers.
- B. The Marketing department believes that the benefits of a good company image, as portrayed by a successful calendar, will last into a second year and bring the same increase in orders.
- C. The calendar will contain photos of both staff and company products.
- D. Increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months.
- E. It will be similar to calendars sent out in previous years
Correct Answer: B,D 🗳️
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
Checkpoint reports are being produced monthly. A week after the last checkpoint report was prepared, the team responsible for developing the 'classroom-based training materials' have realized that they will not be able to deliver the materials to the accreditor by the work package completion deadline.
Which action demonstrates application of the 'manage by exception' principle?
- A. The team manager immediately reports the issue to the project manager.
- B. The team manager reports the issue in the next checkpoint report.
- C. The team manager immediately produces an exception plan to replace the current plan.
- D. The team manager raises a risk that the deadline may be missed.
Correct Answer: A 🗳️
Explanation: Only visible for ActualCollection members. You can sign-up / login (it's free).
MANAGING A STAGE BOUNDARY
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?
- A. Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage
4. - B. Review the performance of the external suppliers who worked on delivery of the 'e-learning course' during stage 3.
- C. Re-plan when the number of learners using the pilot course, and their increased knowledge, will be measured during stage 4.
- D. Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.
Correct Answer: A 🗳️
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The 'classroom-based training materials' will be used as the basis for developing the 'e-learning course'. As a result, the executive wants to ensure that the 'classroom-based training materials' are of the required standard.
The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?
- A. Yes, because the executive should be available to provide ad hoc direction to the project manager.
- B. No, because the project manager should be given authority to manage the project on a day-to-day basis.
- C. No, because the senior user should be responsible for specifying the quality criteria for the training materials.
- D. Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
Correct Answer: B 🗳️
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?
- A. No, because it is the configuration item record of the relevant product description that is updated, not the work package.
- B. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
- C. No, because the work package should be checked to confirm the reporting arrangements of the 'e- learning course'.
- D. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.
Correct Answer: B 🗳️