
Give You Free Regular Updates on PMP Exam Questions Oct 21, 2023
Achieve the PMP Exam Best Results with Help from PMI Certified Experts
NEW QUESTION # 284
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget.
Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
- A. Prioritize which backlog activities should be kept.
- B. Ask for more resources to clear the backlog activities.
- C. Assign an owner for each backlog activity and track progress.
- D. Work on the backlog activities with fewer story points.
Answer: C
NEW QUESTION # 285
You are in the process of controlling changes to a project baseline. Which of the following is the LEAST helpful input?
- A. Work performance information
- B. Cost baseline
- C. Activity cost estimates
- D. Project funding requirements
- E. Performance reports
Answer: C
NEW QUESTION # 286
During a project's planning phase, a functional manager becomes anxious about the impact of the project on team morale and constantly reaches out the project manager with these concerns.
- A. Review the stakeholder engagement plan to ensure the functional manager's interests have been accurately recorded.
- B. Review the project charter with the team to address the functional manager's concerns.
- C. Discuss the functional manager's concerns with the e sponsor.
- D. Expand the project management information system, (PMIS) to allow members to communication their concerns to the functional manager.
Answer: C
NEW QUESTION # 287
Measuring the probability and consequences of risks is part of:
- A. Quantitative risk analysis
- B. Risk management planning
- C. Qualitative risk analysis
- D. Risk identification
Answer: A
Explanation:
Notice, the key word in the first question is "Measuring". This would imply D - quantitative risk analysis. It would not be A, because Risk Management Planning deals with your general approach to managing risk, not with specific risks. Risk Identification doesn't involve any estimation of the probability of a risk or the impact. Qualitative Analysis involves a broad determination of the probability and impact of risks, but I would argue that there is no "measurement" done in qualitative analysis.
NEW QUESTION # 288
On what is project baseline development established?
- A. Actual project cost and schedule
- B. Revised project cost and schedule
- C. Estimated project cost and schedule
- D. Approved product requirements
Answer: C
NEW QUESTION # 289
As a project nears completion the project manager learns that some stakeholders believe that the project failed to meet the schedule and ran over budget The project manager wants to invalidate that belief by providing data on project plans and end results What type of analysis should the project manager conduct?
- A. Regression
- B. Document
- C. Variance
- D. Trend
Answer: C
NEW QUESTION # 290
A project manager needs to obtain a new resource for a project. This will mean engaging the market to contract a resource. Timeframes are tight.
How should the project manager proceed?
- A. Contact someone they know can do the job and procure them
- B. Follow the applicable organizational procurement process
- C. Place an advertisement on a key job website and prepare a contract
- D. Engage a recruitment agent and prepare a contract with the agent
Answer: B
Explanation:
Section: Executing
NEW QUESTION # 291
A key import supply has suffered a delay of 6 months.
The delay affects a functionality that is needed to complete the project on time.
The project manager learns from the project that another team is working on a product that could work as a solution, but it is still a prototype.
What should the project manager do to accelerate this solution?
- A. Contact the other project team and ask them to organize a demo of the prototype
- B. Perform iterative planning with the team to use the prototype
- C. Prioritize the backlog with the customer to remove the feature
- D. Check the burnup charts to see what progress has been made to integrate the solution
Answer: A
NEW QUESTION # 292
A project sponsor comes to the project team with an urgent change. This change was part of the original plan, and the project team is afraid of negative impact.
What should the project manager do?
- A. Submit a change request.
- B. Update the change request process.
- C. Ask the sponsor to maintain the original plan.
- D. Analyze the impact and then implement the change.
Answer: A
NEW QUESTION # 293
An input to the scope change control process is:
- A. Product defects
- B. Work results
- C. Customer requirements
- D. Performance reports
Answer: D
NEW QUESTION # 294
A predictive project team come across a scenario where they need to use some agile tools and methods.
However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
- A. Ensure the project team follows the organizational project management processes.
- B. Prepare a summary and escalate this issue to the project's change control board (CCB),
- C. Create a change request to include the agile methods and proceed to implementation,
- D. Work with the team to determine appropriate project methods and practices and implement them.
Answer: D
NEW QUESTION # 295
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
- A. Organizational process assets.
- B. Enterprise environmental factors.
- C. Work performance information.
- D. Earned value management.
Answer: C
NEW QUESTION # 296
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project What should the project manager do first to determine a governance approach for the project?
- A. Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines
- B. Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project
- C. Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines
- D. Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project
Answer: C
NEW QUESTION # 297
During an audit, a team member complains about the quality of the product being produced. However, no metric related to this complaint was taken into account in the quality management plan.
What should the project manager do?
- A. Analyze the feedback provided by the team member and update the issue log.
- B. Analyze the feedback provided by the team member and initiate a change request if needed.
- C. Schedule a meeting with the team member and the sponsor to discuss the quality issue.
- D. Explain to the team member that the metrics being used to assess quality are standard.
Answer: B
Explanation:
Section: Monitoring and Controlling
NEW QUESTION # 298
Schedule milestones and a predefined budget are examples of:
- A. Organizational process assets.
- B. Activity cost estimates.
- C. Requirements documentation.
- D. Project constraints.
Answer: D
NEW QUESTION # 299
Outputs from constituent processes might be used as:
- A. Proof of process completion.
- B. Inputs to other processes.
- C. Identification of project tasks.
- D. Indicators to eliminate project redundancies.
Answer: B
NEW QUESTION # 300
A project team member has lost enthusiasm and is experiencing low morale for a project they were once excited about. What should the project manager do?
- A. Meet with the team member to understand what the issues are and to provide support.
- B. Escalate the issue to the team member's functional manager and request a response as soon as possible.
- C. Leverage other team members who are contributing and making the project a success.
- D. Have the team member transferred to another project and add other resources to the project.
Answer: A
NEW QUESTION # 301
It is expensive to lease office space in cities around the world. Office space can cost approximately USD $80 per square foot in Tampa, Florida. And it can cost approximately $50,000 per square meter in Tokyo. These
"averages" can help a person to determine how much it will cost to lease office space in these cities based on the amount of space leased. These estimates are examples of______________
- A. Reserve analysis
- B. Bottom-up estimating
- C. Parametric estimating
- D. Variance analysis
Answer: C
Explanation:
Section: Mix Questions
Explanation:
Parametric estimating involves using statistical relationships between historical data and other variables to calculate or estimate for activity parameters, such as cost, budget, or duration. The example is representative of a simple parametric model.
NEW QUESTION # 302
Constructive team roles include:
- A. Encourager, initiator and gatekeeper.
- B. Summarizer, recognition seeker and information seeker.
- C. Information giver, devil's advocate and clarifier.
- D. Withdrawer, harmonizer and blocker.
Answer: A
Explanation:
Constructive and destructive are team roles that indicate how your attitude effects overall team development. A constructive team role is one that helps team development and a destructive one is that which hampers team development. Accordingly, Constructive team roles are:
1.Initiator - lets do this
2.Information seeker - don't we have better information?
3.Information giver - My experience has been that...
4.Encourager - Mary, that was very helpful
5.Clarifiers - I believe we are saying that....
6.Gate Keeper - We have not heard Mary's opinion on this issue yet. What do you think, Mary?
7.Harmonizer - I believe that we are all saying the same thing
8.Summarizer - I feel that we can now reach an agreement As opposed to the above positive roles, Destructive team roles are:
1.Aggressor criticizes and attempts to deflate other
2.Blocker does not want to listen to what other people say
3.Withdrawer is withdrawn
4.Recognition seeker sole purpose is to attract attention and gain recognition
5.Topic jumper jumps topics
6.Dominator dominates the discussion
7.Devil's advocate always pokes hole in other's logic As you can see, B, C and D have a destructive role each. A is the correct answer with all three roles being constructive [Note: Devils Advocate is normally used for a constructive purpose. A person plays the role of negating many suggestions to evoke team members to participate and come up with ideas. It's commonly used as an idea generation technique. Hence I feel Devil's Advocate is not a destructive role. It is true that it can be positive or negative. I have usually seen it classified as "destructive" just because when used in extreme, you really prevent others from feeling safe enough to voice their own opinion.]
NEW QUESTION # 303
......
Detailed New PMP Exam Questions for Concept Clearance: https://www.actualcollection.com/PMP-exam-questions.html
Provide PMP Practice Test Engine for Preparation: https://drive.google.com/open?id=1fMKyar-_1CD_gGP8kv4jZlJYfciUiwvt