NEW QUESTION # 157
Which of the following are typical social considerations throughout the contract life cycle? Select the TWO that apply.
- A. Managing waste
- B. Using recycled materials
- C. Support small local businesses
- D. Health and safety
- E. Minimizing use of non-renewable resources
Answer: C,D
Explanation:
The following are typical social criteria in procurement:
* Reducing unemployment
* Preventing the use of child labour
* Preventing discrimination on the grounds of race, religion, disability, sex or sexual orientation
* Encouraging good employment practice
* Reducing local unemployment
* Reducing social exclusion
* Promoting training opportunities for the young or disadvantaged
* Encouraging access to work for people with disabilities
Reference:
LO 3, AC 3.2
NEW QUESTION # 158
Halfords is a major bicycle and car parts retailer with long history in the market. Its suppliers are plentiful and there is no threat of forward integration. Some other smaller retailers are applying 3D-printing technology to make personalized bicycle parts but their market share is relatively low. 3D-printing technology is an example of which competitive force?
- A. Bargaining power of buyer
- B. New entrants may enter the market
- C. Rivalry within the industry
- D. Threat of substitute
Answer: D
Explanation:
3D-printed parts can replace traditional metal parts. They are also more easily customised to fit customer's needs. This technology is an example of threat of substitute in Porter's Five Forces model.
Substitute goods or services that can be used in place of a company's products or services pose a threat.
Companies that produce goods or services for which there are no close substitutes will have more power to increase prices and lock in favorable terms. When close substitutes are available, customers will have the option to forgo buying a company's product, and a company's power can be weakened.
Reference:
- CIPS study guide page 85-96
- Porter's 5 Forces Definition: Analyzing Businesses (investopedia.com) LO 2, AC 2.2
NEW QUESTION # 159
Lider Ltd is a leading bathroom furniture manufacturer in Indi
a. The company has more than 30 years experience in the market with extended knowledge of engineering and customers' taste. Lider is planning to launch a new type of bath fitting next year which offers Bluetooth connectivity and thermostat display. The company gathers a team of multi-disciplines, including engineering, procurement, sales and marketing. At the first team meeting, the project leader tells the team to discuss which functions will be valued by the customers, and how to deliver those functions with the lowest costs possible. Which of the following describes the process that the project team is undertaking?
- A. Cost analysis
- B. Just in time
- C. Value engineering
- D. Standardisation
Answer: C
Explanation:
From the scenario, you can see that the project team is developing a new product. They start with analysing the functions, and the costs of delivering those functions. This is a typical process of value engineering. You may read more on value engineering from the reference paper.
Reference:
- CIPS study guide page 171-173
- Value Analysis - Norwood Whittle (cimaglobal.com)
- A CASE STUDY ANALYSIS THROUGH THE IMPLEMENTATION OF VALUE ENGI-NEERING (researchgate.net) LO 3, AC 3.4
NEW QUESTION # 160
The procurement team of an IT hardware manufacturer has been set a target by senior management to reduce the rates paid to the sole supplier of a new and innovative power-saving battery. Which action should the procurement team first consider?
- A. Offering economies of scale
- B. Dual or multiple sourcing
- C. Agreeing rebate thresholds
- D. Offering a framework agreement
Answer: B
Explanation:
Detailed Explanation:
Dual or multiple sourcing introduces competition, reducing the sole supplier's bargaining power and leading to cost reductions. Framework agreements (A) or economies of scale (D) may not address the immediate need to reduce rates. Reference: CIPS Level 4, Sourcing Strategies.
NEW QUESTION # 161
A buyer can use sources of information to review indirect costs associated with the manufacture of goods to support supplier negotiations. Is this statement true?
- A. No, because the supplier's quotation is the only source of information
- B. Yes, because the buyer can understand the cost build-up of the goods
- C. Yes, because indirect costs are always variable
- D. No, because the only information available is for direct costs
Answer: B
Explanation:
Detailed Explanation:
Analyzing both direct and indirect costs helps buyers understand cost structures and negotiate effectively.
Indirect costs, like overheads, can be identified through supplier data and market benchmarks, aiding in cost transparency. Reference: CIPS Level 4, Cost Management and Negotiation.
NEW QUESTION # 162
Which of the following are advantages of zero-based financial budgeting?
Use of previous year figures
Emphasis on short-term planning
Budget treated as flexible
Focus on operational issues
- A. 1 and 4 only
- B. 3 and 4 only
- C. 2 and 4 only
- D. 1 and 2 only
Answer: B
Explanation:
Detailed Explanation:
Zero-based budgeting emphasizes starting from scratch and justifying all expenses.
3 (Budget flexibility): Ensures resources are allocated dynamically based on needs.
4 (Focus on operational issues): Encourages alignment with operational priorities rather than historical trends.
Using prior figures (1) is contrary to zero-based budgeting principles. Reference: CIPS Level 4, Financial Planning and Budgeting.
NEW QUESTION # 163
Variances occur when there are differences between the budgeted costs and the actual costs. When are labour cost variances likely to arise?
When the sales prices change over time due to inflation
When there is more overtime than is expected
When a different wage grade of worker is used to complete a task than was planned for When the supplier changes from manual to electronic invoicing systems for all transactions
- A. 1 and 3 only
- B. 2 and 3 only
- C. 2 and 4 only
- D. 1 and 2 only
Answer: B
NEW QUESTION # 164
Department for Transport (DfT) needs to buy new locomotives to expand the capacity of trains fleet. In 2009, they were criticized for beginning the procurement "without any clear idea of how many trains would be needed, which routes they would run on and what form of power would be required". What should procurement manager of DfT do first to manage risk in making the specification?
- A. Assess the potential risks
- B. Implement mitigating actions
- C. Monitor the potential risks
- D. Identify the possible risks
Answer: D
Explanation:
There are 4 steps to risk managing process:
Step 1: Identify hazards
Step 2: Assess the risk
Once a risk has been identified, a risk assessment should be conducted.
You should carry out a risk assessment for any manual tasks identified as being hazardous, unless the risk is well known and you know how to control it. A risk assessment can help you determine, which postures, movements and forces of the task pose a risk, where during the task they pose a risk, why they are occurring and what needs to be fixed.
Step 3: Control the risk
The ways of controlling risks are ranked from the highest level of protection and reliability to the lowest, which is known as the hierarchy of control. You must always aim to eliminate the hazard, which is the most effective control.
Step 4: Review risk control
Control measures that have been implemented must be reviewed, and, if necessary, revised to make sure they work as planned and to maintain a work environment that is without risks to health and safety.
Source: WorkCover Queensland
Reference:
LO 3, AC 3.3
NEW QUESTION # 165
An example of a direct cost is ...
- A. Rent for premises
- B. Raw material
- C. Office cleaning
- D. An overhead expense
Answer: B
NEW QUESTION # 166
A purchaser is looking for alternative supplies if there is a major disruption to their supply chain, including logistics, manufacturing and all support services. Which of the following method is that purchaser applying?
- A. Treat the risk
- B. Tolerate the risk
- C. Terminate the risk
- D. Transfer the risk
Answer: A
Explanation:
Risk control is the process by which an organization reduces the likelihood of a risk event occurring or mitigates the effects that risk should it occur. CIPS preferred way to determine your risk control strategy is to use the four T's Process:
Transferring Risk can be achieved through the use of various forms of insurance, or the payment to third parties who are prepared to take the risk on behalf of the organization Tolerating Risk is where no action is taken to mitigate or reduce a risk. This may be because the cost of instituting risk reduction or mitigation activity is not cost-effective or the risks of impact are at so low that they are deemed acceptable to the business. Even when these risks are tolerated they should be monitored because future changes may make it no longer tolerable.
Treating Risk is a method of controlling risk through actions that reduce the likelihood of the risk occurring or minimize its impact prior to its occurrence. Also, there are contingent measures that can be developed to reduce the impact of an event once it has occurred. Finding an alternative sup-plier is an example of treating the risk.
Terminating Risk is the simplest and most often ignored method of dealing with risk. It is the ap-proach that should be most favored where possible and simply involves risk elimination. This can be done by altering an inherently risky process or practice to remove the risk. The same can be used when reviewing practices and processes in all areas of the business.
If an item presents a risk and can be changed or removed without it materially affecting the busi-ness, then removing the risk should be the first option considered; rather than attempting the treat, tolerate or transfer it.
Reference:
LO 3, AC 3.3
NEW QUESTION # 167
A procurement manager includes provision on recovery from natural disaster into a through-life specification.
Some suppliers suppose that provision is unnecessary. Is procurement manager's action justified?
- A. Yes, because the regulations require contract to have recovery provision
- B. No, because with current technology, natural disaster can't disrupt supply chain.
- C. No, because this provision will incur unnecessary cost to supplier
- D. Yes, because natural disaster may cause risks in organisation's supply chain
Answer: D
Explanation:
Risks like natural disasters - fire, flood, or weather-related event, and cyber-attacks can disrupt the supply chain seriously. Threats and disruptions mean a loss of revenue and higher costs, which leads to a drop in profitability. And businesses can't rely on insurance alone because it doesn't cover all the costs and the customers who move to the competition. Risks must be identified early and supplier should have a plan that ensures continuous operations during disasters.
There are several steps many companies must follow to develop a solid business continuity plan. They include:
- Business Impact Analysis: Here, the business will identify functions and related resources that are time- sensitive. (More on this below.)
- Recovery: In this portion, the business must identify and implement steps to recover critical business functions.
- Organization: A continuity team must be created. This team will devise a plan to manage the disruption.
- Training: The continuity team must be trained and tested. Members of the team should also complete exercises that go over the plan and strategies.
Reference: CIPS study guide page 138.
LO 3, AC 3.2
NEW QUESTION # 168
Which of the following can cause overhead variance? Select TWO that apply:
- A. Decreasing packaging costs
- B. Spike in monthly leasing fee
- C. Decrease in production volume
- D. Spike in material price
- E. Rising production worker's wage rate per hour
Answer: B,C
Explanation:
Overhead variances arise when the actual overhead costs incurred differ from the expected amounts.
Managers want to understand the reasons for these differences, and so should consider computing one or more of the overhead variances described below. Each of these variances applies to a different aspect of overhead expenditures. It is not necessary to calculate these variances when a manager cannot influence their outcome.
Fixed Overhead Spending Variance
The fixed overhead spending variance is the difference between the actual fixed overhead expense incurred and the budgeted fixed overhead expense. An unfavorable variance means that actual fixed overhead expenses were greater than anticipated. The formula for this variance is:
Actual fixed overhead - Budgeted fixed overhead = Fixed overhead spending variance The amount of expense related to fixed overhead should (as the name implies) be relatively fixed, and so the fixed overhead spending variance should not theoretically vary much from the budget.
Fixed Overhead Volume Variance
The fixed overhead volume variance is the difference between the amount of fixed overhead actually applied to produced goods based on production volume, and the amount that was budgeted to be applied to produced goods. For example, a company budgets for the allocation of $25,000 of fixed overhead costs to produced goods at the rate of $50 per unit produced, with the expectation that 500 units will be produced. However, the actual number of units produced is 600, so a total of $30,000 of fixed overhead costs are allocated. This creates a fixed overhead volume variance of $5,000.
Variable Overhead Efficiency Variance
The variable overhead efficiency variance is the difference between the actual and budgeted hours worked, which are then applied to the standard variable overhead rate per hour. The formula is:
Standard overhead rate x (Actual hours - Standard hours)
= Variable overhead efficiency variance
A favorable variance means that the actual hours worked were less than the budgeted hours, resulting in the application of the standard overhead rate across fewer hours, resulting in less expense being incurred.
However, a favorable variance does not necessarily mean that a company has incurred less actual overhead, it simply means that there was an improvement in the allocation base what was used to apply overhead.
Variable Overhead Spending Variance
The variable overhead spending variance is the difference between the actual and budgeted rates of spending on variable overhead. The variance is used to focus attention on those overhead costs that vary from expectations. The formula is:
Actual hours worked x (Actual overhead rate - standard overhead rate)
= Variable overhead spending variance
A favorable variance means that the actual variable overhead expenses incurred per labor hour were less than expected.
In the study guide, CIPS splits overhead variance into volume and expenditure variance. They can be understood as variable and fixed overhead variance respectively.
NEW QUESTION # 169
The procurement officer for Hunter Manufacturing has been tasked to procure a new manufacturing software management system. They have consulted all relevant internal stakeholders and have the following high-level requirements: flexibility throughout the project, and the supplier to recommend the best solutions for building the system. Which type of specification should be developed?
- A. Design
- B. Conformance
- C. Technical
- D. Performance
Answer: D
NEW QUESTION # 170
The position of a product in its life cycle can affect the price that suppliers set. Is this statement correct?
- A. No, customer's perception of value is the ultimate determinant of the suppliers' price
- B. No, in market economy, the state decides the price of all goods and services
- C. Yes, each stage in product life cycle requires different levels of investment in promotion and distribution
- D. Yes, it is always the only factor determining the price
Answer: C
Explanation:
A firm also has to look at a myriad of other factors before setting its prices. Those factors include the offering's costs, the demand, the customers whose needs it is designed to meet, the external environment-such as the competition, the economy, and government regulations-and other aspects of the marketing mix, such as the nature of the offering, the current stage of its product life cycle, and its promotion and distribution. If a company plans to sell its products or services in international markets, research on the factors for each market must be analyzed before setting prices. Organizations must understand buyers, competitors, the economic conditions, and political regulations in other markets before they can compete successfully.
[...]
The costs of the product-its inputs-including the amount spent on product development, testing, and packaging required have to be taken into account when a pricing decision is made. So do the costs related to promotion and distribution. For example, when a new offering is launched, its promotion costs can be very high because people need to be made aware that it exists. Thus, the offering's stage in the product life cycle can affect its price.
Reference:
- CIPS study guide page 90-91
- 15.2 Factors That Affect Pricing Decisions - Principles of Marketing (umn.edu) LO 2, AC 2.2
NEW QUESTION # 171
Which of the following are typical examples of secondary sources of market data? Select TWO that apply.
- A. Communication with suppliers
- B. Supplier marketing publications
- C. Trade fairs and exhibitions
- D. Published market analysis
- E. Price comparison websites
Answer: D,E
NEW QUESTION # 172
Due to increasing demand, a local restaurant is requesting its fish vendor to supply larger quantity. The restaurant manager also asks the vendor whether it is possible to reduce the total price by 5%. This is known as...?
- A. New purchase
- B. Modified rebuy
- C. Straight rebuy
- D. Capital purchase
Answer: B
Explanation:
There are three major types of buying situations, which are new purchase, modified rebuy and straight rebuy.
Three factors make the buying situations be different from the others, customers may face different problems in these situations.
A new purchase is a situation requiring the purchase of a product for the very first time.
A straight rebuy is when a company places a second order with a supplier that is identical to the first purchase it made.
A modified rebuy is when a company orders again from a supplier, but wants to change some as-pect of the order, such as the quantity, packaging, product features, or delivery times. The scenario above is an example of modified rebuy.
Reference:
- What is a straight rebuy example?
- CIPS study guide page 3-4
NEW QUESTION # 173
When procuring an IT equipment, at which stage the buyer's expectations are translated into a technical specification?
- A. In-service support
- B. Design
- C. Installation
- D. Customer support
Answer: B
Explanation:
IT equipment is typically linked with through-life contracts. This type of contract not only deal with the specification and the price of a machinery, but also other stages such as design, manufacture, installation, in-service support, decommission and disposal. Among these stages, the design stage is when buyer's requirements are translated into technically correct specification.
Reference:
LO 3, AC 3.2
NEW QUESTION # 174
OMK is a Russian steel firm that is expanding market abroad. It plans to build a steel plant in a foreign country. Due to intricate technical requirements, the plant design will be very complex. Procurement department or technical department alone cannot draft the specification. OMK senior management decides that this task must be treated as a project. Which of the following should be done before writing the specification for new steel plant?
- A. Develop the performance framework for the supplier
- B. Develop project initial document
- C. Draft the terms and conditions for plant construction contract
- D. Invite suppliers to the tendering process
Answer: B
Explanation:
The writing of a complex specification should be treated as a project because it requires the brain power from different stakeholders. Many tools and processes of project management can be applied to complex specification development. Before engaging with the stakeholders and implementing the project, the project initial document should developed.
A Project Initiation Document (PID) is one of the most important components of project manage-ment, which forms the foundation for a company project. It is a reference point during the entire project, for the client as well as for the project team.
A PID bundles documentation into a logical reference work that collects all important information needed to start and run a project from a good foundation. After that, Project Initiation Document must be transferred to all stakeholders, including business sponsors.
This forms the basis for the project management. The documentation from which the PID is com-posed include the business case in which the project's justification can be found, the communica-tion plan and the project plan.
The PID is composed out of collected information and includes, among others, the following com-ponents:
- Project goal(s); what do you want to achieve with the project?
- Project size; how large is the project, how long does it take and how many people are involved?
- Project organisation; who are involved in the project, what are their tasks, responsibilities and authority?
- Limits and risks; what can cause a project to stagnate and are there risks related to the project?
- Stakeholders; who has a stake in the success of the project?
- Project checks and frame reporting; by carefully taking into account evaluation moments, it is clear to everyone what sample tests can be carried out during the process.
In addition, it is important that the Project Initiation Document also contains the following infor-mation:
- The background and occasion of the project, which together provide information about the con-text.
- The project organisational structure, which describes who has which management responsibility in the project.
- The project quality plan, describing who controls the quality of the products to be delivered and how it will take place.
- The total project planning, including the duration of all activities.
- The exception process, which describes how exceptions are dealt with and the steps of the escalation procedure.
- The risk log, including the measures that will be taken when there are unforeseen risks.
- The documentation structure of the project, in which the encoding and storage of all documents and products to be provided by the project has been recorded in advance.
Reference:
- CIPS study guide page 148
- Project Initiation Document (PID), a project management tool | ToolsHero LO 3, AC 3.3
NEW QUESTION # 175
Which of the following are typical benefits of through-life asset management to buying organisa-tion? Select the TWO that apply.
- A. Lower risks as there are many suppliers accountable for costs and service over the life of the asset
- B. Better capability of supplier over time
- C. Greater supplier's bargaining power
- D. Shorter specifications
- E. Lower total cost of ownership
Answer: B,E
Explanation:
According to Andrew Graves, "Through-life Management involves the life-cycle management of the products, services and activities required to deliver a fully integrated capability to the customer, while reducing the cost of ownership for the customer." Benefits of through-life asset management can be:
- Lower total life-cycle costs
- Better match between the asset and end-user's needs
- Better supplier capabilities over time because it gains experience of buying organisation's needs.
Reference: CIPS study guide page 131
LO 3, AC 3.2
NEW QUESTION # 176
A consulting firm in London had previously had static budgets. They were set once and locked in for the year.
This resulted in departments meeting their budgets early and doing virtually nothing the rest of the accounting period. To address this imbalance, the company tossed out the static budget and developed a new one for each department of the next 18 months. And each month, real sales figures are analyzed against the plan and the budget is adjusted accordingly. Then the company adds another month into the budgeting plan. What type of budget this company is using?
- A. Activity-based budget
- B. Rolling budget
- C. Incremental budget
- D. Zero-based budget
Answer: B
Explanation:
A rolling budget is continually updated to add a new budget period as the most recent budget period is completed. Thus, the rolling budget involves the incremental extension of the existing budget model. By doing so, a business always has a budget that extends one year into the future.
Think of continuous (rolling) budgets as waves rolling ashore on the beach. A new wave comes in each time, replacing the one that was there before. From a financial perspective, the wave is your budget, and the time between waves is longer! These reporting time frames can be monthly, quar-terly, yearly, etc.
An incremental budget is a budget prepared using a previous period's budget or actual performance as a basis with incremental amounts added for the new budget period.
Zero-based budgeting (ZBB) is a method of budgeting in which all expenses must be justified for each new period. The process of zero-based budgeting starts from a "zero base," and every function within an organization is analyzed for its needs and costs. Budgets are then built around what is needed for the upcoming period, regardless of whether each budget is higher or lower than the previous one.
Activity-based budgeting (ABB) is a system that records, researches, and analyzes activities that lead to costs for a company. Every activity in an organization that incurs a cost is scrutinized for potential ways to create efficiencies. Budgets are then developed based on these results.
Reference: CIPS study guide page 52-59
LO 1, AC 1.4
NEW QUESTION # 177
A procurement organisation is keen to encourage innovation available within the supply market in the execution of an upcoming significant contract opportunity. A team member suggests that the specification should define the performance indicators so that supplier's solution can be checked against them. Which of the following will enable the organisation to achieve this goal?
- A. Using an outcome focused specification
- B. Establishing transparent selection criteria
- C. Using an output focused specification
- D. Applying a precise performance framework
Answer: C
Explanation:
The buying organisation is keen to encourage innovation so they should use the outcome or output based specification. In an outcome-based specification, umbrella statements like 'good quality', 'ambient temperature', 'convenient way' are often used. This may confuse the suppliers, and it's hard to check the solution that supplier offers. On the other hand, ouput-based specifications often include measurable requirements. For example, a specification for air conditioning system states that the system should maintain the room temperature at 19-24 degrees Celsius. Therefore, output specification is more appropriate in this case.
Reference: CIPS study guide page 119-124
LO 3, AC 3.1
NEW QUESTION # 178
Honda of America Manufacturing is a well established automobile manufacturer. It purchases tens of thousands of materials and parts from suppliers, however, only few of them are strategic. To these suppliers, Honda's procurement manager requires them to send details of labour, materials, overhead cost and profit. However, the suppliers are reluctant to submit such confidential infor-mation. Is the procurement manager's action appropriate?
- A. No, because no suppliers are willing to show sensitive information on their costs and profit.
- B. No, because procurement manager should conduct life-cycle analysis
- C. Yes, because the procurement manager can get a good insight from the market
- D. Yes, because strategies can be introduced for reducing cost and improving the supplier relationships.
Answer: D
Explanation:
With strategic suppliers, the aim should be to work co-operatively with them to find ways of reducing costs to achieve a target cost. It is necessary to work with the suppliers in carrying out open book costing by having first persuaded them of the need to do it. Open book can be used to establish a Target Cost, a Compensation Event value and can eventually be used to ensure the payment of actual costs to an organization. A number of forms of contract cater for this functionality of which only the NEC goes to into any great depth of methodology.
If the suppliers worry about leak of confidential information, procurement team can suggest them to sign a non-disclosure agreement. The buying organisation should also comply with data protection regulations. The Employer / individual responsible for a project's costs should ultimately take a pragmatic and sensible approach with regard to commercially or personally sensitive data provided by the contractor. The primary goal of all open book cost management is to provide Employer comfort and security in the accuracy of commercial data; this effectively means striking a balance between undertaking full audits and blind faith.
Reference:
LO 1, AC 1.2
NEW QUESTION # 179
A buyer in Housing Authority is considering using performance specification in upcoming social housing project. What should buyer be aware when using this type of specification?
- A. Using performance specification means that the buyer will bear all the risks regarding the fitness for purpose of the facility.
- B. In performance specification, specific brands and preferred suppliers must be appointed to avoid the competition
- C. The buyer must be able to define the materials to be used, the execution and installation methods required and the specific design of the building
- D. The buyer must be able to clearly define the performance metrics to ensure that the of-fered solution will achieve the desired outcome
Answer: D
Explanation:
In construction, specifications are written documents that describe the materials and workmanship required for a development. They do not include cost, quantity or drawn information but need to be read alongside other contract documentation such as quantities, schedules and drawings.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by a contractor or sup-plier, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Prescriptive specifications give the client more certainty about the end product when they make their final investment decision (i.e. when they appoint the contractor), whereas a performance specification gives the contractor and suppliers more scope to innovate and adopt cost effective methods of work, potentially offering better value for money.
Typically, performance specifications are written on projects that are straight-forward, standard building types, whereas prescriptive specifications are written for more complex buildings, or buildings where the client has requirements that might not be familiar to contractors and where certainty regarding the exact nature of the completed development is more important to the client.
Performance specification has some disadvantages:
- Well-defined performance metrics are needed to ensure that the specified performance will achieve the desired outcome
- Require reliable, practical, economical tests of performance
- Evaluations are subjective and require additional time and effort to complete Therefore, if a performance specification is used, the buying organisation will have to ensure that they are able to define and conduct tests on whether supplier's solution can deliver the desired out-come.
NEW QUESTION # 180
Interserve is a construction contractor in UK. When receiving a huge and complex project, Inter-serve's procurement manager assesses the risks by quantifying them and recommends other stake-holders to plan mitigating actions. Is the procurement manager's action justified?
- A. Yes, because procurement manager needs to assess the risks to prioritise and mitigate any potential risks
- B. No, because embedding the risk into pricing will decrease the company's competitiveness
- C. No, because no risks can be quantified, therefore the procurement manager's action is impossible.
- D. Yes, because all the risks should be quantified and eliminated completely before they happen
Answer: A
Explanation:
Assessing the risks by quantifying them should be done. Even with qualitative risk assessment, quantifying is still important since risks need to be prioritised.
Risk assessment can be qualitative or quantitative. Perform qualitative and perform quantitative risk analysis are two processes within the project risk management knowledge area, in the planning process group. While qualitative risk analysis should generally be performed on all risks, for all projects, quantitative risk analysis has a more limited use, based on the type of project, the project risks, and the availability of data to use to conduct the quantitative analysis.
Qualitative Risk Analysis
A qualitative risk analysis prioritises the identified project risks using a pre-defined rating scale. Risks will be scored based on their probability or likelihood of occurring and the impact on project objectives should they occur.
Probability/likelihood is commonly ranked on a zero to one scale (for example, .3 equating to a 30% probability of the risk event occurring).
The impact scale is organizationally defined (for example, a one to five scale, with five being the highest impact on project objectives - such as budget, schedule, or quality).
A qualitative risk analysis will also include the appropriate categorization of the risks, either source-based or effect-based.
Quantitative Risk Analysis
A quantitative risk analysis is a further analysis of the highest priority risks during a which a numerical or quantitative rating is assigned in order to develop a probabilistic analysis of the project.
A quantitative analysis:
- Quantifies the possible outcomes for the project and assesses the probability of achieving specific project objectives
- Provides a quantitative approach to making decisions when there is uncertainty
- Creates realistic and achievable cost, schedule or scope targets
In order to conduct a quantitative risk analysis, you will need high-quality data, a well-developed project model, and a prioritized lists of project risks (usually from performing a qualitative risk analysis).
Reference: CIPS study guide page 143-144
LO 3, AC 3.3
NEW QUESTION # 181
......
CIPS L4M2 (Defining Business Needs) certification exam is a highly respected qualification that is recognized globally. It is designed for procurement and supply chain management professionals who are looking to advance their careers and demonstrate their knowledge and skills in this field. By passing L4M2 exam, candidates can enhance their career prospects and demonstrate their commitment to excellence in procurement and supply chain management.