The PRINCE2 Foundation written exam is the first step towards becoming a certified PRINCE2 practitioner. PR2F exam tests the candidate's understanding of the PRINCE2 methodology and their ability to apply it to real-world scenarios. PRINCE2 7 Foundation written Exam certification is ideal for individuals who want to understand the basic principles of project management and are looking to establish a career in project management. The PRINCE2 methodology provides a structured approach to project management that emphasizes on dividing projects into manageable stages, and the PRINCE2 Foundation certification equips individuals with the knowledge and skills required to contribute to a PRINCE2 project team.

 

NEW QUESTION # 97
Who is responsible for documenting any tailoring of the business case theme?

  • A. Business project assurance
  • B. Corporate management
  • C. Project manager
  • D. Executive

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 98
What is a description of a leadership activity within a project?

  • A. Creating a stage plan and product descriptions for the products to be created in the next stage
  • B. Understanding and working with different departments outside of the project team
  • C. Agreeing a work package with a team manager to deliver products using specific tools
  • D. Ensuring that a co-located project team uses the agreed communication methods

Answer: C

Explanation:
A leadership activity within a PRINCE2 project involves several responsibilities, one of which is agreeing on work packages with team managers. This agreement includes specifying the tools and techniques to be used for product delivery. This activity is crucial for ensuring clarity and mutual understanding of how work is to be conducted, facilitating effective delegation and accountability within the project team.
(PRINCE2 7 Foundation Study Guide, AXELOS)


NEW QUESTION # 99
How does product-based planning help to determine the project approach?

  • A. By Identifying the outputs that the project trust deliver
  • B. By planning in detail how to deliver the outputs over a more predictable time scale
  • C. By dividing the delivery of the project's outputs into stages which do not overlap
  • D. By managing constraints to the planned completion date for the project

Answer: A

Explanation:
Product-based planning in PRINCE2 focuses on defining and understanding the project's outputs or products.
This method helps in determining the project's approach by clarifying what products must be delivered, thus guiding the planning of activities and resources needed to create these products. It ensures that the project's structure and execution strategy are aligned with delivering tangible, well-defined outcomes.References:
PRINCE2 7 Foundation resources on product-based planning.


NEW QUESTION # 100
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project

  • A. 1 and 4
  • B. 1 and 2
  • C. 3 and 4
  • D. 2 and 3

Answer: D


NEW QUESTION # 101
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

  • A. Only the Project Board
  • B. Only corporate or programme management
  • C. All levels of management
  • D. Only the Project Manager

Answer: C

Explanation:
The mechanisms established by the Progress theme in PRINCE2 are used by all levels of management to control any unacceptable deviations. This includes the Project Board, Project Manager, and higher management levels, ensuring that everyone involved in the project management team can effectively monitor and control the project's progress and address issues as they arise. References: PRINCE2 Foundation manual, PRINCE2 official resources


NEW QUESTION # 102
Who is responsible for documenting any tailoring of the business case theme?

  • A. Business project assurance
  • B. Corporate management
  • C. Project manager
  • D. Executive

Answer: C

Explanation:
In PRINCE2, the responsibility for documenting any tailoring of the Business Case theme, along with other themes, generally falls to the Project Manager. This includes documenting how the theme is being applied in a particular project context, ensuring the approach remains appropriate and meets the project's requirements.References: PRINCE2 Foundation Manual


NEW QUESTION # 103
Which is NOT a purpose of the Initiating a Project process?

  • A. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • B. Enable a Project Board decision about the commitment of resources to a project
  • C. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • D. Establish solid foundations for a project

Answer: C

Explanation:
This statement is not true as the purpose of the Initiating a Project process. The correct purpose of this process is to ensure that there are solid foundations for the project, usually after the project has already been decided as worthwhile and approved for initiation. The decision to initiate a project is typically made before the Initiating a Project process. References: PRINCE2 Foundation official documentation and study materials.


NEW QUESTION # 104
Which statement defines a risk?

  • A. An event that has already occurred that the Project Manager must deal with immediately
  • B. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
  • C. A certain event occurring in the future that will have a negative impact on the project's objectives
  • D. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

Answer: D


NEW QUESTION # 105
Which is NOT considered when defining risk tolerance?

  • A. An organization's risk appetite
  • B. The allocated risk budget
  • C. The amount of risk a Project Board considers acceptable
  • D. A Project Board's attitude towards risk taking

Answer: B


NEW QUESTION # 106
Which is a purpose of a Project Product Description?

  • A. Shows the dependencies between the project's products to aid planning
  • B. Records the costs and timescales for delivery of the project's final product
  • C. Defines what theproject must deliver in order to gain acceptance
  • D. Provides a list of all the products to be delivered by the project

Answer: C


NEW QUESTION # 107
Which is an objective of the Closing a Project process?

  • A. Review the performance of the project against its baseline
  • B. Review and approve the plan for project closure
  • C. Create a Benefits Review Plan
  • D. Perform any post-project reviews

Answer: A

Explanation:
The objective of the Closing a Project process in PRINCE2 includes reviewing the performance of the project against its baseline. This ensures that all objectives have been achieved, the project has delivered the required products, and stakeholders are satisfied with the outcomes. It provides a formal closure to the project by ensuring all project work is completed and assessed. References: PRINCE2 Foundation manual, PRINCE2 official resources


NEW QUESTION # 108
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?

  • A. Preparing a schedule
  • B. Organizing work packages
  • C. Defining and analysing the products
  • D. Preparing estimates

Answer: C

Explanation:
In the 'planning' technique of PRINCE2, understanding what makes the outputs acceptable to the users occurs during the step of "Defining and Analyzing the Products." This step involves detailed discussions about product requirements and specifications to ensure clarity on what the project must deliver for it to be accepted by the users. It sets out the criteria that the products must meet to satisfy the user's needs and expectations.References: (PRINCE2 7 Foundation Handbook, AXELOS)


NEW QUESTION # 109
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Specify the desired result
  • B. Provide the resources and skills to deliver the desired result
  • C. Develop a project's products
  • D. Ensure the technical integrity of a project

Answer: A

Explanation:
Section: Volume A


NEW QUESTION # 110
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity

  • A. Transfer
  • B. Share
  • C. Avoid
  • D. Reduce

Answer: B


NEW QUESTION # 111
Which is NOT one of the PRINCE2 integrated elements?

  • A. The processes
  • B. Tailoring PRINCE2 to the project environment
  • C. The themes
  • D. The products

Answer: D


NEW QUESTION # 112
What may be funded from a risk budget?

  • A. Corrections required due to off-specifications
  • B. Implementation of a fallback plan
  • C. Preparation of the risk management approach
  • D. Impact analysis of requests for change

Answer: B

Explanation:
Reference http://prince2.wiki/Risk#Risk_Budget


NEW QUESTION # 113
What do customer's quality expectations identify?

  • A. Skills required to develop the project product
  • B. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
  • C. Reviewer names for each product
  • D. Standards that must be used in order to meet the level of quality needed

Answer: D


NEW QUESTION # 114
Which is a purpose of the Plans theme?

  • A. Establish the project's structure of accountability
  • B. Identify, assess and control any potential changes to the baseline
  • C. Understand whether the targets are achievable
  • D. Assess and control uncertainty

Answer: C


NEW QUESTION # 115
Which is an objective of the 'directing a project' process?

  • A. To select and appoint the project manager
  • B. To design the project management team roles
  • C. To give authority to deliver the project product
  • D. To create the plan to deliver the project product

Answer: C

Explanation:
An objective of the 'Directing a Project' process in PRINCE2 is to give authority to deliver the project product. This process is where the project board makes key decisions and exercises overall control while delegating day-to-day management of the project stages to the project manager.References: PRINCE2 Foundation Manual


NEW QUESTION # 116
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance

  • A. 3 and 4
  • B. 1 and 4
  • C. 1 and 2
  • D. 2 and 3

Answer: A

Explanation:
Reference http://prince2.wiki/Managing_Product_Delivery


NEW QUESTION # 117
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

  • A. Create user and supplier groups
  • B. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
  • C. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
  • D. Create a separate Project Board to manage the supplier elements of the project

Answer: A


NEW QUESTION # 118
As a minimum requirement for applying the risk theme, what must specifically be assessed?

  • A. Whether a risk may impact the underlying technical assumptions
  • B. Whether a risk may affect the project-level quality tolerances
  • C. Whether a risk may cause the project to exceed its cost tolerance
  • D. Whether a risk may alter the project's business justification

Answer: D

Explanation:
According to the PRINCE2 risk management approach, a minimum requirement for applying the risk theme is to assess whether a risk may alter the project's business justification. This assessment ensures that risks are identified, analyzed, and managed in relation to their potential impact on the project's ability to deliver its intended benefits and justify the investment.
= PRINCE2 7 Foundation handbook and online resources


NEW QUESTION # 119
......


The PRINCE2-Foundation Exam covers the basic principles, themes, and processes of project management. PR2F exam is administered by accredited training organizations and consists of 60 multiple-choice questions that must be completed within 60 minutes. The passing score for the exam is 55%, and candidates must demonstrate an understanding of the concepts and principles of PRINCE2 to pass the exam.


The PRINCE2 Foundation exam is a written exam that tests candidates on their knowledge and understanding of the PRINCE2 methodology. PR2F exam consists of 60 multiple-choice questions, and candidates have one hour to complete the exam. The pass mark for the exam is 55%, which means that candidates must answer at least 33 questions correctly to pass the exam.

 