Ultimate Guide to Prepare Free Scrum PSM-III Exam Questions & Answer [Q11-Q32]

Share

Ultimate Guide to Prepare Free Scrum PSM-III Exam Questions and Answer

Pass Scrum PSM-III Tests Engine pdf - All Free Dumps

NEW QUESTION # 11
Mid-sprint a development team forecasts it will not be able to deliver all the planned backlog items. They are worried andask for your advice as Scrum Master. What will you tell them?

Answer:

Explanation:
When a Development Team realizes mid-Sprint that it may not be able to deliver all planned Sprint Backlog Items, this situation should be handled throughempiricism, not concern or blame. As a Scrum Master, I would reassure the team and guide them back to Scrum principles.
First, I would remind the team that in Scrum they donot commit to delivering all Sprint Backlog Items.
Instead, the Scrum Team commits todoing their very best to achieve the Sprint Goal. Discovering additional work, complexity, or unknowns during the Sprint is expected, especially in complex product development. The Sprint Backlog is a forecast, not a fixed contract.
Second, I would help the team assess theimpact of what they have discovered. If the newly discovered work is minor and theSprint Goal is still within reach, the team can continue as planned while adapting the Sprint Backlog as needed. This reflects normal inspection and adaptation during the Sprint.
Third, if the impact is significant and threatens the Sprint Goal, the Development Team should have a focused discussion aboutif and how the Sprint Goal can still be met. This may involve changing the approach, reducing scope while preserving the Sprint Goal, or identifying alternative ways to deliver the intended value.
In such cases, theProduct Owner should be involvedin the conversation. Including the Product Owner increases transparency and enables faster value-based decision-making, such as re-negotiating scope or adjusting priorities while keeping the Sprint Goal intact. This collaboration ensures that adaptations are aligned with product value.


NEW QUESTION # 12
When working on one software product with multiple Scrum teams in Scrum Nexus, what is important about dependenciesof the planned Backlog Items and integration of the work being done?

Answer:

Explanation:
When multiple Scrum Teams work together on a single product usingScrum Nexus, managing dependencies and ensuring effective integration are critical to delivering a usable Increment each Sprint. Scrum Nexus extends Scrum by explicitly addressing the complexity that arises from multiple teams working on the same product.
First,dependencies between teams should be minimized. Dependencies reduce autonomy, slow feedback, and increase risk. In Nexus, Product Backlog Items should be ordered and refined in such a way that work with strong dependencies is keptwithin a single team whenever possible. This supports cross-functionality at the team level and reduces the coordination overhead required between teams.
Second, when dependencies cannot be avoided, they must be madetransparent and actively managed. The Nexus framework encourages early identification of dependencies during Nexus Sprint Planning so that teams can coordinate their work effectively. However, the goal remains to continuously reduce dependencies over time through better backlog ordering, architecture improvements, and skill broadening.
Third,integration of work is vital and takes precedence over completing all planned work. In Scrum Nexus, an Increment is only considered "Done" when the work of all teams is fully integrated and meets the shared Definition of Done. Unintegrated work, even if technically complete by an individual team, does not provide value and increases risk.
Fourth, integration must occurearly and often during the Sprint, not only at the end. Continuous integration helps uncover issues sooner, supports frequent inspection, and enables timely adaptation. Delaying integration increases the likelihood of defects, rework, and failure to produce a usable Increment.


NEW QUESTION # 13
Decisions to optimise value and control risk are made based on the perceived state of the artefacts. What events and practises can improve transparency over the artefacts? Explain why.

Answer:

Explanation:
In Scrum, decisions to optimize value and control risk depend on theperceived state of the artifacts. If artifacts are not transparent, inspection and adaptation become ineffective, leading to poor decisions. Scrum therefore defines specificevents and practicesto improve transparency and support empirical decision- making.
Scrum Events That Improve Artifact Transparency
Sprint Planningimproves transparency by aligning the Scrum Team on the current state of theProduct Backlogand theProduct Increment. The Product Owner explains backlog ordering and objectives, while Developers assess what is feasible based on the current Increment and Definition of Done. This shared understanding reduces risk by creating a realistic Sprint Goal.
Daily Scrumimproves transparency of theSprint Backlog. Developers inspect progress toward the Sprint Goal and make visible emerging risks, dependencies, and impediments. Daily inspection ensures that deviations are discovered early, enabling fast adaptation and reducing delivery risk.
Sprint Reviewimproves transparency of theProduct IncrementandProduct Backlog. Stakeholders directly inspect the Increment and provide feedback. This exposes assumptions, validates value, and informs Product Backlog adaptation, helping optimize future value and reduce market risk.
Sprint Retrospectiveimproves transparency ofprocess-related aspectsthat influence the artifacts. By inspecting ways of working, tools, skills, and the Definition of Done, the team identifies improvements that increase artifact quality and reliability over time.
Practices That Improve Transparency
Aclear and shared Definition of Doneensures transparency of the Product Increment. It creates a common understanding of what "complete" means and prevents hidden work or misleading progress.
Product Backlog refinementimproves transparency by clarifying Product Backlog Items, making assumptions explicit, and reducing uncertainty. Although not a formal Scrum event, refinement supports better inspection and forecasting.
Frequent integration and testingimprove transparency by making the real state of the Increment visible early and often. This reduces the risk of late surprises and unintegrated work.
Visible metrics and information radiators(such as Sprint Goals, Sprint Backlogs, and progress toward objectives) help stakeholders and teams understand the state of work without relying on reports or interpretations.


NEW QUESTION # 14
In what ways does the Scrum Master attend the Sprint Retrospective?

Answer:

Explanation:
The Sprint Retrospective is a formal Scrum event where the Scrum Team inspects how the last Sprint went with respect toindividuals, interactions, processes, tools, and their Definition of Done, and identifies improvements for future Sprints. The Scrum Master attends the Sprint Retrospective inmultiple, complementary ways, consistent with the Scrum Guide.
First, the Scrum Masterjoins the Sprint Retrospective as a Scrum Team member. The Scrum Guide defines the Scrum Team as consisting of the Product Owner, Developers, and the Scrum Master. Therefore, the Scrum Master is not an external observer but afull participantin the event. As such, the Scrum Master activelyinspects people, processes, and tools, and contributes insights based on their perspective and experience, while remaining respectful of the team's self-management.
Second, the Scrum Master oftenfacilitates the Sprint Retrospective. According to the Scrum Guide, the Scrum Master is accountable for ensuring that Scrum events take place and are productive. Facilitation may include helping the team create a safe environment, encouraging openness, ensuring balanced participation, keeping the discussion focused on improvement, and helping the team stay within the timebox. However, facilitation does not imply control; the Scrum Master facilitatesto serve the team, not to direct outcomes.
Third, the Scrum Mastersupports empiricism during the Retrospective. By fostering transparency, encouraging honest inspection, and helping the team identify actionable improvements, the Scrum Master strengthens the Scrum pillars oftransparency, inspection, and adaptation. The Scrum Master may also help the team turn improvement ideas into concrete actions that can be planned for the next Sprint.
Finally, the Scrum Master helps ensure that the Sprint Retrospective results inmeaningful adaptation. While the Scrum Team decides what improvements to implement, the Scrum Master supports the team in identifying impediments, coaching on improvement techniques, and helping remove organizational or systemic obstacles that are beyond the team's direct control.
In summary, the Scrum Master attends the Sprint Retrospective byjoining as a full Scrum Team member, participating in inspection,often facilitating the event, andsupporting continuous improvement and empiricism. This balanced participation ensures that the Retrospective remains a powerful mechanism for learning and adaptation rather than a ritualistic meeting.


NEW QUESTION # 15
What variables should a Product Owner consider when ordering the Product Backlog?

Answer:

Explanation:
Ordering the Product Backlog is a key accountability of theProduct Ownerand is essential for maximizing value through empiricism. The ordering reflects continuous inspection of multiple variables, not a single prioritization rule.
1. Value and Outcomes
The primary variable isvalue. The Product Owner considers:
* Customer and user value,
* Business impact and outcomes,
* Alignment with theProduct Goal.
Items that deliver higher or more urgent value are generally ordered higher.
2. Risk and Uncertainty
Items that reducerisk or uncertaintyare often ordered earlier. This includes:
* Technical risk,
* Market or usability risk,
* Integration or dependency risk.
Early learning enables better decisions and reduces long-term cost.
3. Dependencies
The Product Owner considersdependenciesbetween backlog items and teams. Items that unblock other work or reduce dependencies may be ordered higher to improve flow and reduce coordination overhead.
4. Effort, Complexity, and Feasibility
While Developers estimate effort, the Product Owner uses this information to balance value againstcost, complexity, and feasibility. High-value items that are feasible within near-term constraints are often prioritized.
5. Feedback and Learning
Ordering reflectsfeedback from Sprint Reviews, user testing, and market response. Items may move up or down based on what has been learned from previous Increments.
6. Time Sensitivity and Opportunity Cost
Some items are time-critical due to:
* Regulatory deadlines,
* Market windows,
* Competitive pressure.
Delaying such items may reduce or eliminate their value.


NEW QUESTION # 16
Every Sprint has a Sprint Review. What is the purpose and result of this event?

Answer:

Explanation:
TheSprint Reviewis a formal Scrum Event held at the end of each Sprint toinspect the outcome of the Sprint andadapt the Product Backlogif needed. Its primary purpose is to enable empirical decision-making by involving both theScrum Team and stakeholdersin inspecting the product and determining what to do next.
Purpose of the Sprint Review
The main purpose of the Sprint Review is toinspect the "Done" Product Incrementin the context of overall product progress. During this event:
* The Scrum Team presents the Increment that meets the Definition of Done.
* The Developers explain what was delivered, what was not delivered, and the challenges encountered.
* Stakeholders activelyinspect the product, often by using it, rather than reviewing documents or reports.
This inspection provides real, hands-on feedback and creates a shared understanding of the current state of the product and its direction.
Result of the Sprint Review
The Sprint Review results inheightened transparencyfor all participants. By jointly inspecting the Increment, new insights emerge about customer needs, market conditions, risks, and opportunities. These insights inform conversations aboutwhat is needed next.
Based on this shared understanding:
* TheProduct Owner collaborates with stakeholders and the Scrum Teamto adapt and update the Product Backlog.
* Completed work is accepted or further work is identified.
* New Product Backlog Items may be added, reordered, or refined to reflect the latest understanding of the product.
The Sprint Review does not aim to approve or reject work formally, but to enable learning and adaptation.


NEW QUESTION # 17
How the organization discusses and plans the work of creating software will be reflected in the implementation of that software.
Technical systems can be decomposed to composite elements, from the large to the small. Basic components may be represented as activities, workflows, functions, features, capabilities, and other similar nomenclature.
How does this system decomposition affect Scrum Teams on scaled projects?

Answer:

Explanation:
How an organization discusses, plans, and decomposes work is inevitably reflected in the software it produces. When technical systems are decomposed into elements such as activities, workflows, functions, features, or components, these decomposition choices have adirect and systemic impact on Scrum Teams, especially inscaled Scrum environments.
1. Decomposition Influences Team Structure (Conway's Law)
In scaled projects, system decomposition often drives how teams are formed. When work is decomposed along technical components or functions, organizations tend to createspecialist or component teams(e.g., front- end teams, back-end teams). This results in:
* Increaseddependencies between teams,
* More handoffs and coordination,
* Reduced autonomy of individual teams.
Scrum, however, expects teams to becross-functionaland capable of delivering usable Increments independently. Component-based decomposition therefore hinders effective Scrum adoption at scale.
2. Effect on Value Delivery and Transparency
Scrum relies on frequent inspection ofintegrated, working product Increments. When decomposition focuses on small technical parts rather thanend-to-end features or capabilities, teams may deliver partial outputs instead of usable value.
This negatively affects:
* Transparency, as progress is reported through intermediate artifacts rather than working software,
* Inspection, since stakeholders cannot meaningfully evaluate value,
* Adaptation, because feedback is delayed until integration occurs.
In scaled Scrum, this often results in "almost done" work that is not truly Done.
3. Feature-Oriented Decomposition Supports Scrum
Scrum scales more effectively when system decomposition emphasizesvertical slices of value, such as features or capabilities, rather than horizontal technical layers. Feature-oriented decomposition enables:
* Cross-functional teams,
* Reduced dependencies,
* Faster feedback cycles,
* Independent delivery of value by each team.
This approach aligns with Scrum's expectation that every Sprint produces ausable Increment.
4. Impact on Integration and Risk
Decomposition decisions strongly affectintegration frequency. Poor decomposition increases integration complexity and encourages late integration, which raises risk and reduces learning.
In Scrum-especially at scale-integration must happen early and often. Unintegrated work is not considered Done, and delayed integration undermines empiricism by hiding real system behavior until late in development.
5. Learning and System Optimization
When Scrum Teams work on complete features rather than isolated components, they gain broader insight into:
* Customer needs,
* System-wide trade-offs,
* End-to-end product behavior.
This shared understanding improves decision-making and supportscontinuous improvement at the system level, rather than local optimization within silos.


NEW QUESTION # 18
Your Scrum Team has one month Sprints. The development team argues that since this period is quite long, a Daily Scrum isa bit too much. They instead want a weekly update meeting. What is your opinion on this?

Answer:

Explanation:
From a Scrum Master's perspective, replacing the Daily Scrum with a weekly update meeting isnot consistent with Scrumand would significantly weaken the team's ability to inspect and adapt effectively, regardless of the Sprint length.
First, Scrum explicitly defines theDaily Scrum as a required event. The Scrum Guide states that the Daily Scrum is a 15-minute event held every working day of the Sprint for the Developers. The length of the Sprint-whether one week or one month-does not change the purpose or necessity of this event. Therefore, by choosing not to have a Daily Scrum, the team wouldno longer be practicing Scrum, but rather a Scrum- like process.
Second, the Daily Scrum isnot a status meeting. Its primary purpose is to allow the Developers toinspect progress toward the Sprint Goal, synchronize their work, andadapt the Sprint Backlogas needed. A weekly meeting dramatically reduces the frequency of inspection and adaptation, delaying the discovery of issues such as integration problems, misalignment, or risks to the Sprint Goal.
Third, removing the Daily Scrum negatively impactstransparency, one of Scrum's three pillars of empiricism. Without daily synchronization, important information about progress, impediments, and discoveries becomes stale or hidden. This reduced transparency increases the likelihood that work will drift away from agreed standards, fail to integrate properly, or no longer support the Sprint Goal by the end of the Sprint.
Fourth, the argument that a one-month Sprint justifies less frequent inspection reflects a misunderstanding of empiricism. Longer Sprintsincrease risk, which makes frequent inspection and adaptation more important, not less. The Daily Scrum provides a regular opportunity to realign the team and respond early to emerging problems, thereby reducing waste and rework.
Finally, as a Scrum Master, my role is toteach and coachthe Scrum Team on the purpose and value of Scrum events. Rather than removing the Daily Scrum, I would help the Developers improve how they use it-for example, ensuring it focuses on progress toward the Sprint Goal and actionable planning for the next 24 hours, instead of turning into a reporting session.


NEW QUESTION # 19
What would be an example of a development team member displaying unethical behaviour?

Answer:

Explanation:
An example of unethical behaviour by a Development Team member in Scrum isknowingly delivering low- quality or non-secure softwarewhile being aware of the potential negative impact on users, stakeholders, or the organization. Such behaviour contradicts the ethical expectations embedded in Scrum and violates multiple Scrum Values.
For instance, a developer may intentionally ignore known defects, security vulnerabilities, or technical debt in order to finish work faster or appear more productive. Releasing software that is known to be insecure or unstable places end-users at risk and misrepresents the true state of the product. This underminesCommitment to quality andCourage, as the individual avoids addressing difficult issues or raising concerns.
Another unethical example iswithholding important informationfrom the Scrum Team or stakeholders. This may include hiding risks, downplaying impediments, or not being transparent about progress or challenges.
Such behaviour violatesOpennessand damages trust, which is essential for empiricism and effective collaboration.
Unethical behaviour may also be expressed throughfailing to support team members. For example, refusing to help others, dismissing or disrespecting colleagues' opinions, or working in ways that harm team cohesion contradicts the Scrum Value ofRespect. Scrum expects team members to collaborate and support each other in achieving the Sprint Goal.
Finally,going against agreements made by the Scrum Team, such as ignoring the Definition of Done or agreed working agreements, is unethical. This damages accountability and can mislead stakeholders about the quality and completeness of the work.


NEW QUESTION # 20
What artifacts are part of Scrum, and during which Scrum Events are they likely to be the subject of inspection?

Answer:

Explanation:
Scrum defines three coreartifactsthat provide transparency into the work being done and the value being delivered: theProduct Backlog, theSprint Backlog, and theProduct Increment. Each artifact is inspected at specific Scrum Events to support empiricism throughtransparency, inspection, and adaptation.
Product Backlog
TheProduct Backlogis an ordered list of everything that is known to be needed in the product and is the single source of work for the Scrum Team.
* It isinspected during Sprint Planning, where the Scrum Team selects Product Backlog Items to work on and aligns them with the Sprint Goal.
* It is alsoinspected during the Sprint Review, where stakeholders and the Scrum Team review progress and adapt the Product Backlog based on feedback and new insights.
* In addition, the Product Backlog is continuously inspected and adapted duringBacklog Management (often called refinement). While this activity is essential, it isnot a Scrum event in the strict sense.
Sprint Backlog
TheSprint Backlogconsists of the Sprint Goal, the selected Product Backlog Items for the Sprint, and a plan for delivering them.
* It iscreated and inspected during Sprint Planning, where the Developers forecast the work needed to achieve the Sprint Goal.
* It isinspected daily during the Daily Scrum, as Developers assess progress toward the Sprint Goal and adapt their plan accordingly.
* It may also beinspected during the Sprint Reviewto provide transparency into what was planned versus what was accomplished.
Product Increment
TheProduct Incrementis the sum of all completed Product Backlog Items during the Sprint and previous Sprints that meet the Definition of Done.
* It isinspected during Sprint Planning, to understand the current state of the product and determine what can be built next.
* It isinspected during the Sprint Review, where stakeholders evaluate the Increment and provide feedback.
* The Increment may also be inspected at any time to support transparency and decision-making.
Continuous Inspection Beyond Events
While Scrum defines specific events where artifacts are commonly inspected, the Scrum Guide emphasizes thatartifacts may be inspected at any time, as long as the inspection does not hinder progress. Scrum encouragesfrequent inspectionto enable timely adaptation and reduce risk.


NEW QUESTION # 21
In what way does Scrum encourage ethical behaviour, doing "the right thing", in software development?

Answer:

Explanation:
Scrum encourages ethical behaviour in software development by creating a framework that promotes transparency, accountability, quality, and respect for stakeholders, all of which are grounded in the Scrum Values. Rather than prescribing ethical rules, Scrum embeds ethical behaviour into the way work is organized and delivered.
First, Scrum promotes ethics through its focus ondelivering valuable, high-quality working products. The Scrum Guide emphasizes delivering usable Increments that meet a shared Definition of Done. By prioritizing quality and value for both the organization and end-users, Scrum discourages practices such as cutting corners, hiding technical debt, or delivering misleading progress, which are ethically questionable.
Second, Scrum strongly supportstransparency, a core pillar of empiricism. All significant aspects of the work-such as progress, impediments, risks, and uncertainties-are made visible through artifacts and events.
This transparency encourages honesty about what can and cannot be achieved and prevents unethical behaviour such as misreporting status or concealing problems until it is too late.
Third, Scrum encouragesaccountabilityat both individual and team levels. Clear accountabilities for the Product Owner, Developers, and Scrum Master ensure that responsibility is not diffused or avoided. Teams are accountable for delivering value, improving their way of working, and meeting their commitments. This accountability fosters ethical decision-making and ownership of outcomes.
Fourth, Scrum supports ethical behaviour throughcontinuous learning and improvement. Sprint Retrospectives create a structured opportunity to reflect on mistakes, share knowledge, and improve processes and practices. This openness to learning promotes humility, integrity, and a willingness to correct issues rather than ignoring or rationalizing them.
Finally, Scrum is explicitly guided by theScrum Values of Commitment, Courage, Focus, Respect, and Openness, which form its ethical foundation.
* Commitmentencourages teams to do what they say they will do.
* Courageenables individuals to raise concerns, admit problems, and challenge unethical practices.
* Focushelps teams concentrate on delivering real value rather than superficial outputs.
* Respectensures consideration for colleagues, stakeholders, and end-users.
* Opennesspromotes honesty about progress, challenges, and uncertainty.


NEW QUESTION # 22
The developers in your Scrum Team raise an impediment. The work planned for upcoming Sprint involves certain knowledge and expertise they do not possess within the team. How do you handle this impediment?

Answer:

Explanation:
When Developers raise the lack of certain knowledge or expertise as an impediment, the Scrum Master must address the situation in a way that reinforcesScrum principles, especiallycross-functionality, empiricism, and self-management, while also supporting value delivery.
First, it is essential to verify whether this is truly animpediment. In Scrum, an impediment is something the team cannot resolve on its own. As a Scrum Master, I would facilitate a discussion with the Developers and, if appropriate, the Product Owner to inspect whether the expertise is genuinely required to achieve the desired outcome. In some cases, the scope or approach can be adapted, or the Product Backlog Item can be refined so that alternative solutions are viable. This conversation may reveal that the need for specialized knowledge is less critical than initially assumed.
Second, if the expertise is indeed necessary, the Scrum Master should encourage the team to address the issue as across-functional Scrum Team. Scrum expects teams to have, or acquire, all skills needed to deliver value. Therefore, I would ask the Developers how they couldlearn or acquire the necessary knowledge themselves. Possible options include allocating time for learning, research, training, experimenting, or building a prototype. These activities can be planned as part of the Sprint Backlog and support long-term team capability.
Third, the Scrum Master can help the team make effective use ofoutside expertise without undermining self- management. During Sprint Planning or refinement, the team may consult internal or external experts to gain insights, validate approaches, or reduce uncertainty, while still retaining ownership of the work and the Sprint Backlog.
Finally, if none of these options resolve the impediment, the Scrum Master has a responsibility tohelp the organization support the Scrum Team. This may involve facilitating access to expertise from elsewhere in the organization or, if necessary, from outside the organization. The Scrum Master does not solve the problem personally but works to remove organizational barriers so the team can proceed.


NEW QUESTION # 23
You have been appointed the Scrum Master for a brand new product your organization is planning to develop.
A ProductOwner has also been appointed. Initially, fifteen developers will work on the product. What approaches are common forforming teams for this product, and how do they likely benefit or hinder the Product Development effort?

Answer:

Explanation:
When starting development of a brand new product with fifteen developers, forming effective teams is a critical early decision that significantly influences the success of product development. From a Scrum Master' s perspective, multiple approaches are commonly used in practice. Each approach offers distinct benefits and drawbacks when evaluated against Scrum principles such asself-organization, cross-functionality, and value delivery.
1. Facilitating Teams to Self-Organize
One common approach is tofacilitate the developers in forming teams themselves. This approach aligns strongly with Scrum, as the Scrum Guide states that Scrum Teams areself-managingand decide internally how best to accomplish their work.
Benefits:
Allowing teams to self-organize promotesempowerment, ownership, and accountability. Developers can use their existing knowledge of each other's strengths, weaknesses, and working styles to form balanced teams. This often increases motivation and psychological safety, both of which support high performance.
Hindrances:
For a new product, this process can bemessy and time-consuming, especially if developers lack experience in forming effective teams. Teams may optimize for comfort or familiarity rather than cross-functionality, potentially leading to skill gaps or imbalanced teams.
2. Forming Two or Three Cross-Functional Feature Teams
Another common approach is to deliberately formtwo or three cross-functional feature teams, each containing all the skills necessary to deliver working product increments.
Benefits:
This approach closely matches how Scrum describes teams.Cross-functional feature teamscan independently deliverintegrated, "Done" Incrementsof the product, improving flow, reducing dependencies, and supporting empiricism. All necessary skills are available within the team, enabling faster inspection and adaptation.
Hindrances:
In the context of a brand new product, teams may not yet knowwhich skills are actually required, making it difficult to form truly balanced teams upfront. Additionally, specialists may feel isolated and lose regular interaction with peers who share the same expertise across teams.
3. Forming Teams Based on Specialization (Component Teams)
A third approach is to organize teams according totechnical specialization, such as front-end and back-end teams. These are often referred to ascomponent teams.
Benefits:
This structure allows specialists to work closely together, enablingfast knowledge sharing, technical consistency, and deep expertisein specific components of the system. It can feel efficient, especially in the early stages of development.
Hindrances:
From a Scrum perspective, this approach significantly hindersvalue delivery. Component teams struggle to deliver complete, integrated features independently and introduce dependencies and handoffs. This makes it harder to produce a usable Increment each Sprint and isnot how Scrum describes teams, even though it remains a commonly used strategy in many organizations.
Scrum Master Perspective and Conclusion
As a Scrum Master, my role is not to mandate a single team structure, but tocoach and facilitatethe organization toward structures that best enable Scrum. While all three approaches are seen in practice, Scrum clearly favorsself-organizing, cross-functional feature teamsbecause they maximize learning, transparency, and the ability to deliver value each Sprint.


NEW QUESTION # 24
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities.
Which two activities are part of the Product Owner role according to Scrum?

Answer:

Explanation:
According to Scrum, theProduct Owneris accountable formaximizing the value of the productand for effectiveProduct Backlog management. Two key activities that are explicitly part of this role are:
1. Ordering the Product Backlog to Maximize Value
The Product Owner is responsible forordering the Product Backlogso that the most valuable work is done first. This ordering reflects:
* Business and customer value,
* Risk and uncertainty,
* Strategic goals and learning from previous Sprints.
Through this activity, the Product Owner ensures that the Scrum Team is always working on what matters most.
2. Ensuring Product Backlog Items Are Transparent, Clear, and Understood The Product Owner ensures that Product Backlog Items are:
* Clearly expressed,
* Transparent to the Scrum Team and stakeholders,
* Understood well enough for Developers to select them during Sprint Planning.
This does not mean writing detailed requirements alone, butcollaboratingso that shared understanding exists.


NEW QUESTION # 25
......

Professional Scrum Master level III (PSM III) Practice Tests 2026 | Pass PSM-III with confidence!: https://drive.google.com/open?id=1yayHRdaT5ooLY5ksBQ_eFkFGTsAvENRB

Online Exam Practice Tests with detailed explanations!: https://www.actualcollection.com/PSM-III-exam-questions.html