From a free demo to 365 days of updates and a clearly stated refund policy, ActualCollection covers every step of your Nokia SDM Certification - NI preparation in one place. Thousands of candidates in 2026 start their SDM_2002001050 journey right here.
Nokia SDM_2002001050 Exam Overview:
| Certification Vendor: | Nokia |
|---|---|
| Exam Name: | SDM Certification - NI |
| Exam Number: | SDM_2002001050 |
| Available Languages: | English |
| Real Exam Qty: | 160 |
| Sample Questions: | ![]() |
| Exam Way: | Online or onsite proctored exam via Pearson VUE |
| Official Syllabus URL: | https://www.nokia.com/networks/training/onc/exams/ |
Nokia SDM_2002001050 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Service Delivery Management (SDM) | - Customer and Stakeholder Management
|
| Project Management & Delivery | - Project Planning and Execution
|
| Risk and Change Management | - Change Control Process
|
Common Questions About the Nokia SDM Certification - NI Exam
The Nokia SDM Certification - NI exam is the official Nokia test registered under exam code SDM_2002001050. Passing it earns you the Nokia Certification certification. Nokia exams are valued because they test job-ready skills, so a passing score here carries real weight on a resume.
Yes. ActualCollection offers a free PDF demo of the Nokia SDM Certification - NI material so you can judge the question quality and format before spending anything. After purchase, your license includes 365 days of free updates, and if you want to keep receiving updates after that period, renewals are available at a 50% discount.
If you take the Nokia SDM Certification - NI exam within 60 days of your purchase and do not pass, ActualCollection backs you with a 100% money-back guarantee. The claim must match the exam your product covers: attempts taken within 3 days of purchase are not eligible (that is too little preparation time), and neither are downloaded-but-unused products, free materials, or expired orders. The candidate name must match the payer name, and you need to submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Prefer not to refund? You can swap instead and receive two other exam products of equal value for free while keeping the update service on your original purchase.
Delivery itself is instant: your files are downloadable right away and emailed to you within one minute of payment. If nothing arrives within 2 hours, contact customer service. There is no limit on how many computers you may install the software on.
The official Nokia SDM Certification - NI syllabus is organized into 3 domains. Key areas include Service Delivery Management (SDM), Project Management & Delivery, and Risk and Change Management. The complete, up-to-date topic list appears in the exam topics section above; work through it line by line and flag anything you cannot yet explain in your own words.
Nokia SDM Certification - NI Sample Questions:
Question 1
What is the purpose of a Project Target Agreement?
A. 1) full or partial agreement between Tender PM and Project Execution PM of the project base lines and the contract terms at the end of the handover process 2) PM's formal confirmation that all relevant information from tender phase was handed over 3) release of tendering team
B. 1) agreement between PM and his line manager of the project targets relevant for Short Term Incentive 2) PM's confirmation that he is aware of and accepts his incentive relevant project objectives
C. 1) agreement between the PM and the customer of the project targets and the contract terms at the start of project execution 2) formal approval of the customer that the PM proposed by NSN is considered acceptable from customer's perspective
D. 1) full or partial agreement between CT Head and respective PM on the project base lines and the contract terms at the end of the handover process 2) PM's formal confirmation that all relevant information from tender phase was handed over 3) release of tendering team
Question 2
When is the right moment to freeze the project scope considering the case life cycle ?
A. At project closure.
B. During the Handover from business acquisition to project delivery phase (Gate 6 - PTA).
C. During project execution.
D. Before Gate 4.
Question 3
In which phase of the project MUST the PM report and negotiate changes in the scope of work?
A. When the total amount of the Changes start to impact the project final Gross Margin.
B. During project execution and in agreement with CT's strategy towards the Customer.
C. During project closure.
D. When the Customer requests quotation for a next phase.
Question 4
A subcontractor approved and selected by Procurement is working for your Project but delivering installations with too many items in the Punch List. Which of the following actions would you choose first?
A. Cancel new PO's to this subcontractor.
B. Stop the payment for this subcontractor until quality issues are solved.
C. Refer to the contractual Quality Requirements and develop a recovery plan with the Subcontractor.
D. Disqualify the company and ask Procurement for a new supplier.
Question 5
Why are PARD (Project Asset Rotation Days) and TILT (Telecom Implementation Lead-Time) KPI's closely related to each other?
A. Because both KPI's are NI project related.
B. Because both KPI's are CT cash flow related.
C. Because TILT is influenced by the PARD KPI (influenced = if one is decreasing the other is also decreasing).
D. Because PARD is influenced by the TILT KPI (influenced = if one is decreasing the other is also decreasing).
Solutions:
| Question 1 Answer: D | Question 2 Answer: B | Question 3 Answer: B | Question 4 Answer: C | Question 5 Answer: D |