ActualCollection RCDD Dumps Real Exam Questions Test Engine Dumps Training
BICSI RCDD exam dumps and online Test Engine
BICSI RCDD Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
NEW QUESTION 57
Exhibit:
The figure below represents what type of chart?
- A. Gantt
- B. Milestone
- C. PERT
- D. Calendar
- E. Status
Answer: B
Explanation:
Topic 14, Private CATV Distribution Systems
NEW QUESTION 58
Buildings larger than ________ must contain a dedicated room for the termination of entrance facilities.
- A. 13,300 square m (140,000 square ft)
- B. 5529 square m (60,000 square ft)
- C. 11,160 square m (120,000 square ft)
- D. 7389 square m (80,000 square ft)
- E. 9300 square m (100,000 square ft)
Answer: E
NEW QUESTION 59
The information technology system (ITS) designer should design conduits entering a building from below grade point to extend ________ above finished floor (AFF).
- A. 254 mm (10 in)
- B. 203 mm (8 in)
- C. 100 mm (4 in)
- D. 51 mm (2 in)
- E. 152 mm (6 in)
Answer: C
Explanation:
Topic 21, Data Centers
NEW QUESTION 60
Which of the following is NOT a type of intrusion detection system sensor?
- A. Time-auxiliary
- B. Electromechanical
- C. Vibration
- D. Thermal
- E. Capacitance
Answer: A
Explanation:
Topic 20, Outside Plant
NEW QUESTION 61
Class ________ administration provides for the telecommunications infrastructure administration needs of a single building, or of a tenant served by a single or multiple. It also includes administration for backbone cabling, systems, and.
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 62
An offset in a conduit run should be considered the equivalent of a 90 degree bend.
- A. False
- B. True
Answer: B
NEW QUESTION 63
Aerial pole bending moments are usually controlling at unguyed corners and dead ends.
- A. False
- B. True
Answer: B
NEW QUESTION 64
A product is listed after it successfully completes a series of which of the following test?
- A. Electrical
- B. Regulatory codes
- C. Mechanical
- D. Thermal
Answer: A,C,D
NEW QUESTION 65
The required minimum clearance of telecommunication cable above street and driveway surfaces is which of the following?
- A. 23.5 feet vertically
- B. 18 feet vertically
- C. 15.5 feet vertically
- D. 10 feet vertically
Answer: C
NEW QUESTION 66
A work breakdown structure is:
- A. Reflective of project organizational structure
- B. A set of accounting codes
- C. A replacement for a Gantt chart
- D. Influenced by market conditions at the time of the project execution
- E. Easily standardized
Answer: D
NEW QUESTION 67
The must be critically involved early in the construction project, long before the plans are finalized.
- A. False
- B. True
Answer: B
NEW QUESTION 68
Class C suspension strands are used for corrosive environments such as in industrial or coastal area.
- A. False
- B. True
Answer: B
NEW QUESTION 69
How many storm loading areas are there in the contiguous United States?
- A. Two
- B. Three
- C. One
- D. Six
- E. Four
- F. Five
Answer: B
NEW QUESTION 70
For design purposes, loudspeakers are rated for a measured sound pressure level (SPL) at:
- A. 3 m (10 ft) from the loudspeaker with 2 watts of power input
- B. 1 m (3.3 ft) from the loudspeaker with 1 watt of power input
- C. 3 m (10 ft) from the loudspeaker with 1 watt of power input
- D. 1 m (3.3 ft) from the loudspeaker with 2 watts of power input
Answer: B
NEW QUESTION 71
All of the following are considered market or regional conditions that can impact construction costs EXCEPT:
- A. Displacement and relocation
- B. Construction time frame
- C. Seasonal effects on construction costs
- D. Other large projects in the area
Answer: A
NEW QUESTION 72
What device is used in both wired and wireless networks to link network access devices?
- A. Switch
- B. Gateway
- C. Router
- D. Bridge
Answer: D