Latest [Jan 04, 2022] SAP C-TS412-1909 Exam Practice Test To Gain Brilliante Result [Q16-Q31]

Share

Latest [Jan 04, 2022] SAP C-TS412-1909 Exam Practice Test To Gain Brilliante Result

Take a Leap Forward in Your Career by Earning SAP C-TS412-1909


SAP C-TS412-1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.


C-TS412-1909 Exam Certification Details:

Languages:English
Sample Questions: SAP C-TS412-1909 Exam Sample Question
Duration:180 mins
Cut Score:51%
Level:Associate
Exam:80 questions

 

NEW QUESTION 16
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project type
  • B. In the project profile
  • C. In the operative WBS element
  • D. In the project version
  • E. In the project definition of a standard WBS

Answer: B,C,E

 

NEW QUESTION 17
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Plant
  • B. Sales organization
  • C. Controlling area
  • D. Operating concern
  • E. Company code

Answer: A,C,E

 

NEW QUESTION 18
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • B. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

Answer: D

 

NEW QUESTION 19
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.

  • A. Utilize priorities for setting the user status.
  • B. Ensure user status must always be set manually.
  • C. Allow business processes forbidden by SAP system status.
  • D. Restrict setting user status for individual users.

Answer: A,D

 

NEW QUESTION 20
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

  • A. Saving a purchase order
  • B. Saving a supplier invoice
  • C. Saving a service entry sheet
  • D. Saving a goods receipt

Answer: C,D

 

NEW QUESTION 21
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Activity allocation
  • B. Calculation of actual values
  • C. Creation of purchase orders
  • D. Goods receipt for purchase orders

Answer: C

 

NEW QUESTION 22
Which object is relevant in assembly processing to create an assembly order for the SD document?

  • A. Control key
  • B. Requirement class
  • C. Item category
  • D. Project profile

Answer: B

 

NEW QUESTION 23
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • B. Set up the requirement date manually as February 5.
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
  • D. Set up the requirement date aligned with the activity start date and an offset of 5 days.

Answer: D

 

NEW QUESTION 24
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Sales order items
  • C. Project definition
  • D. WBS elements

Answer: B,D

 

NEW QUESTION 25
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

  • A. Planned dates
  • B. Baseline dates
  • C. Basic dates
  • D. Forecast dates

Answer: C,D

 

NEW QUESTION 26
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching for the individual status
  • B. By searching via status combination code
  • C. By searching via status selection profile
  • D. By searching for the status profile

Answer: A,D

 

NEW QUESTION 27
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations can create purchase requisitions.
  • B. Multiple project simulations can be used simultaneously.
  • C. Project simulations can be used to plan structures and costs.
  • D. Project simulations allow posting of actual data.
  • E. Project simulations can be created without using an operational project as a template.

Answer: B,C,E

 

NEW QUESTION 28
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
  • B. The purchase order is updated automatically to match the new quantity while saving the project.
  • C. The system automatically creates a new purchase requisition with the difference to the original quantity.
  • D. A workflow can be triggered to inform the purchasing group.

Answer: D

 

NEW QUESTION 29
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • B. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
  • D. Earliest dates and latest dates are scheduled by forward scheduling.

Answer: A

 

NEW QUESTION 30
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. By default, critical activities have a float time, which is less than or equal to zero.
  • B. Activities with the time constraint "Must start on" always have a negative float time.
  • C. Float time can be negative.
  • D. The maximum size of a free float is as large as the total float of an activity.
  • E. The float time of WBS elements is calculated by extrapolation.

Answer: A,B,C

 

NEW QUESTION 31
......


SAP C-TS412-1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones

Material > 12%

Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Resources > 12%

Describe how the Resource Planning process integrates with HCM

Cost and Budgets > 12%

Describe procedures for establishing budgets and reporting costs.

Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports

Revenues and Payments > 12%