NEW QUESTION 28
What master data in the activity type is used to post an activity allocation?

  • A. Primary cost element
  • B. Non-operating expense
  • C. Secondary cost element
  • D. Balance sheet account

Answer: C

 

NEW QUESTION 29
In what step of the purchase-to-pay process is a purchase requisition generated?

  • A. Vendor selection
  • B. Invoice verification
  • C. Source of supply determination
  • D. Determination of requirements

Answer: D

 

NEW QUESTION 30
Which of the following master records are directly assigned to a company code? There are TWO correct answers for this Question

  • A. Fixed asset
  • B. Material master
  • C. Cost center
  • D. Activity type

Answer: A,C

 

NEW QUESTION 31
What must two company codes have in common if you want to link them to the same controlling area? There are TWO correct answers for this Question

  • A. Operational chart of accounts
  • B. Company code currency
  • C. Country
  • D. Fiscal year variant

Answer: A,D

 

NEW QUESTION 32
Which SAP solution is used to perform marketing operations within the SAP S/4HANA suite?

  • A. SAP Hybris
  • B. SAPAriba
  • C. SAP SuccessFactors
  • D. SAP Fieldglass

Answer: A

 

NEW QUESTION 33
Which of the following areas are part of SAP SuccessFactors Employee Central? There are THREE correct answers for this Question

  • A. Employee Data
  • B. Payroll
  • C. Organization management
  • D. Success and Development
  • E. Learning Management

Answer: A,B,C

 

NEW QUESTION 34
Which objects can you settle?
There are Three correct answers for this Question

  • A. Cost center
  • B. Profitability segment
  • C. Maintenance order
  • D. Work breakdown structure (WBS) element

Answer: C,D

 

NEW QUESTION 35
How do you use the result of a released standard cost estimate? There are THREE correct answers for this Question

  • A. To calculate the price of an activity type
  • B. To update the current standard price in the material master record
  • C. To determine the base costs used to calculate overhead
  • D. To calculate the plan costs in a production order
  • E. To determine a material sales price in Sales and Distribution

Answer: A,B,D

 

NEW QUESTION 36
What is the hierarchical model of a project?

  • A. Project definition
  • B. Task list
  • C. Network
  • D. Work breakdown structure

Answer: D

 

NEW QUESTION 37
At which points in the order-to-cash process are postings made to the general ledger?
There are TWO correct answers for this Question

  • A. Saving the invoice
  • B. Saving the sales order
  • C. Posting a goods issue
  • D. Confirming a transfer order

Answer: A,C

 

NEW QUESTION 38
What does a depreciation area control?
There are TWO correct answers for this Question

  • A. Asset class
  • B. Estimated useful life
  • C. Depreciation accounts
  • D. Depreciation start date

Answer: B,D

 

NEW QUESTION 39
What is the result of posting a vendor's invoice?

  • A. The material document is generated
  • B. The vendor's account is cleared of open items
  • C. The purchase requisition is updated
  • D. The PO history is updated

Answer: D

 

NEW QUESTION 40
In which situation would you create an equipment master record? There are TWO correct answers for this Question

  • A. To report and track preventive maintenance tasks for an object
  • B. To report the effects of usage on the likelihood of damage to the installed equipment
  • C. To functionality represent the technical system structures in your company
  • D. To report the usage time of an object at a functional location

Answer: A,D

 

NEW QUESTION 41
You purchase raw materials with a purchase order against an internal order. During which process step are journal entries posted?

  • A. Release purchase order
  • B. Save purchase requisition
  • C. Post valuated goods receipt
  • D. Calculate the payment method

Answer: C

 

NEW QUESTION 42
Which enterprise structure elements are in a sales area? There are TWO correct answers for this Question

  • A. Plant
  • B. Distribution channel
  • C. Company code
  • D. Division

Answer: B,D

 

NEW QUESTION 43
What needs to be entered to create a business partner? There are TWO correct answers for this Question.

  • A. Business partner role
  • B. Partner functions
  • C. Business partner type
  • D. Account group

Answer: A,D

 

NEW QUESTION 44
What can a successful MRP run create?

  • A. Planned independent requirements
  • B. Reservations
  • C. Purchase orders
  • D. Dependent requirements

Answer: D

 

NEW QUESTION 45
What are some of the characteristics of the SAP Fiori UX There are TWO correct answers for this Question

  • A. Adaptive to devices
  • B. Role-based applications
  • C. single access entry point
  • D. Function-based applications

Answer: B,C

 

NEW QUESTION 46
You need stock materials to complete your maintenance process. At what steps can a material reservation be created? There are TWO correct answers for this Question

  • A. Release an order
  • B. Technically complete an order
  • C. Save an order
  • D. Settle an order

Answer: A,B

 

NEW QUESTION 47
......