
[Jan 04, 2022] Latest C-TS422-2020 Exam with Accurate SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing PDF Questions
Practice To C-TS422-2020 - ActualCollection Remarkable Practice On your SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Exam
C-TS422-2020 Exam Certification Details:
| Duration: | 180 mins |
| Sample Questions: | SAP C-TS422-2020 Exam Sample Question |
| Level: | Associate |
| Languages: | English |
| Exam: | 80 questions |
| Cut Score: | 56% |
NEW QUESTION 10
A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?
- A. Change the special procurement key of the phantom assembly in the BOM.
- B. Change the item category of the phantom assembly in the BOM.
- C. Change the explosion type of the phantom assembly in the BOM.
- D. Change the phantom item indicator for the phantom assembly in the BOM.
Answer: C
NEW QUESTION 11
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Consumption-based planning
- B. Manual planning without check
- C. Material requirements planning
- D. Forecast planning
Answer: A
NEW QUESTION 12
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Cost-related
- B. Order-related
- C. Milestone-related
- D. Product-related
Answer: B,D
NEW QUESTION 13
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a negative offset time in the strategy profile.
- B. Specify a positive planning horizon in the strategy profile.
- C. Specify a negative planning horizon in the strategy profile.
- D. Specify a positive offset time in the strategy profile.
Answer: A
NEW QUESTION 14
Which of the following is a valid sequence of the main activities in product on order processing?
- A. Creation, scheduling, release, material withdrawal, confirmation
- B. Creation, staging, release, material withdrawal, confirmation
- C. Creation, scheduling, release, variance calculation, confirmation
- D. Creation, release, scheduling, material withdrawal, confirmation
Answer: A
NEW QUESTION 15
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. The Change Planning Direct on indicator is set.
- C. Alternative resources are fully occupied.
- D. The work center has several individual capacities.
Answer: A,D
NEW QUESTION 16
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
- A. To increase the number of planning levels
- B. To make the assignment of components easier
- C. To reduce the number of material masters
- D. Tosimplify the structure of bills of material
- E. To reduce the number of changes required in bills of material
Answer: B,D,E
NEW QUESTION 17
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planned order's components are copied from the picking list.
- B. The planned order is converted to a production order.
- C. The planned order generates capacity requirements.
- D. The planned order's component availability is checked
Answer: C
NEW QUESTION 18
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
- A. Use batch determination.
- B. Use the material where-used report.
- C. Use the material staging report.
- D. Use the batch information cockpit.
Answer: D
NEW QUESTION 19
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Creation of a purchasing contract
- B. Change of the material'sprocurement type
- C. Creation of dependent requirements
- D. Change of the storage bin
- E. Creation of a sales order
Answer: B,C,E
NEW QUESTION 20
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?
- A. The most restrictive status
- B. The cross-plant status
- C. The least restrictive status
- D. The plant-specific status
Answer: A
NEW QUESTION 21
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?
- A. Kanban
- B. Production order release
- C. Material requirements planning
- D. Back flushing
Answer: C
NEW QUESTION 22
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.
- A. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
- B. Add the agreement to the source list and mark itfor MRP relevance.
- C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- D. Add the agreement to the quota arrangement and mark it for MRP relevance.
Answer: B,C
NEW QUESTION 23
How can you set up the supply source for the SAP Kanban process? Note: There are 3correct answers to this question.
- A. Using purchasing costs for automated source prioritization
- B. Using quotations for internal and external procurement
- C. Using stock transfer reservations for stock transfer
- D. Using run schedule quantities for in-house production
- E. Using purchase orders for external procurement
Answer: C,D,E
NEW QUESTION 24
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run?Note:
There are 2 correct answers to this question.
- A. Use a specific MRP controller.
- B. Use a specific MRP type.
- C. Use a specific material group
- D. Use a specific material status.
Answer: A,B
NEW QUESTION 25
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers tothis question.
- A. Safety stock
- B. Purchase orders
- C. Maximum stock level
- D. Lot size
Answer: A,D
NEW QUESTION 26
......
SAP C-TS422-2020 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Demand Management in SAP S/4HANA < 8% | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. |
| Capacity Planning in SAP S/4HANA 8% - 12% | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. |
| Advanced Planning in SAP S/4HANA > 12% | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts |
| Introduction to SAP S/4HANA Supply Chain Planning < 8% | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. |
| Production Orders in SAP S/4HANA > 12% | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. |
| Master Data in SAP S/4HANA > 12% | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. |
| Material Requirements Planning in SAP S/4HANA 8% - 12% | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. |
| Introduction to SAP S/4HANA Production Planning < 8% | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. |
| Process Orders in SAP S/4HANA < 8% | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). |
| Lean Manufacturing in SAP S/4HANA 8% - 12% | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. |
Exam Questions and Answers for C-TS422-2020 Study Guide Questions and Answers!: https://www.actualcollection.com/C-TS422-2020-exam-questions.html