Top Scrum PSM-II Exam Audio Study Guide! Practice Questions Edition


How to Prepare For Scrum PSM II: Professional Scrum Master II Exam

Preparation Guide for Scrum PSM II: Professional Scrum Master II Exam

Introduction

SCRUMstudy is the national Scrum and Agile certification accreditation body. SCRUMstudy provides education, training, resources, and certifications to practitioners of Scrum and agile. Authorized Training Providers (A.T.P.s), being the biggest collaborator network of SCRUMstudy, provides a platform to deliver training and certifications.

According to SCRUMstudy, Scrum Master Certified professionals are facilitators who ensure that the Scrum Team has an atmosphere conducive to the successful completion of the project. The Scrum Master acts as the guide, facilitator, and teaches Scrum activities to all participants in the project; eliminates challenges for the team; and, ensures the follow-up of Scrum processes.

The PSM II exam has the aim to verify that the applicants have acquired the requisite knowledge of SCRUM application in SCRUM adaptation projects to a particular scenario. Candidates, with powerful agile practices learned, will be acknowledged as part of an elite group of professionals from Scrum who provide experience well beyond what a traditional project manager might contribute.

This guide provides a detailed overview of the Scrum Master Certified PSM II certification including all sorts of PSM II dumps, the exam format, topics covered, exam difficulty and PSM II practice exams, and the target audience profile.


How to book the Scrum PSM II: Professional Scrum Master II Exam

Follow the steps listed below to apply for the Scrum PSM II: Professional Scrum Master II Exam:

  • Step 1: Visit the Scrum Master Certified PSM II section under the “Certifications” tab on the SCRUMstudy website.
  • Step 2: Register your account and click Apply for the exam.
  • Step 3: Pay $250 or use a voucher.
  • Step 4: Submit required documents online.
  • Step 5: Access Scrum Master Certified course (Online or Instructor-led) and get a copy of guide books.
  • Step 6: Schedule the two-hour exam online.

Introduction to Scrum PSM II: Professional Scrum Master II Exam

The Professional Scrum MasterTM level II (PSM II) assessment is available to anyone who wishes to demonstrate his or her ability to apply the Scrum framework to solving advanced, complex problems in the real world. Those that pass the assessment will receive the industry-recognized PSM II Certification as an indication of their advanced knowledge and abilities about Scrum and the role of the Scrum Master.

Anyone attempting the PSM II should have advanced Scrum knowledge, in-depth Scrum experience, and/or have taken the Professional Scrum Master course before taking this assessment. However, attending a course is neither necessary nor sufficient for certification. The PSM II assessment is very difficult and consists of multiple-choice questions based on your knowledge of Scrum and how you would handle real-world situations. Preparation of the exam should be started with PSM II dumps.

 

NEW QUESTION 52
As a Scrum Master, you observe that the Product Owner is not collaborating with the Development Team effectively.
What action would you take?

  • A. Nominate a proxy Product Owner.
  • B. Coach the Product Owner.
  • C. Send the Product Owner to training.
  • D. Act as the go-between.

Answer: B

Explanation:
A Scrum Master coaches those inside and outside the team on the values of Scrum and incremental delivery.

 

NEW QUESTION 53
Individual Development Team members have been approaching Steven, the Scrum Master, to complain about Chris. Chris has the most experience on the system they are building. He often Question:s the choices team members make in design and architecture making them feel bad.
What are two good ways for Steven to address this problem? (Choose two.)

  • A. Steven takes the time between Sprints to organize a team building session to build a stronger relationship.
  • B. Steven suggests facilitating a session with the full team to help resolve the issue.
  • C. Steven observes whether this topic is raised at the Sprint Retrospective. If not, then he checks with the team on how comfortable they are with the way the design and architecture is being handled.
  • D. Steven shares his concerns with Chris and the impact on the other team members and that he should be a team player.
  • E. Steven tells the concerned members that Chris' opinions should be respected as he has the most experience and understands what is best for long term sustainability.

Answer: B,C

Explanation:
Conflicts are a natural occurrence and the Scrum Master coaches the Development Team on the value of resolving conflicts. Leaving conflicts unresolved can impact the Scrum values of openness and respect diminishing trust. Lower trust levels will impact the Scrum Team's effectiveness and can cause impediments in the future. It is the responsibility of the Scrum Master to remove impediments that hinder the team through conflict resolution and facilitation.

 

NEW QUESTION 54
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team's Definition of Done.
What two things should happen with the item? (Choose two.)

  • A. Do not include the item in the Increment for the Sprint.
  • B. Estimate the remaining work needed to make it 'done' and add it to the Product Backlog for the Product Owner to decide what to do with it.
  • C. Split the item and add the estimation of the completed work to the current Sprint so not to impact the velocity and add the 'undone' work to the next Sprint.
  • D. It will be inspected at the Sprint Review and if it is acceptable by the stakeholders then include it in the Increment.

Answer: A,B

Explanation:
At the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's definition of 'Done'. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and it is used to assess when work is complete on the product Increment.

 

NEW QUESTION 55
A new Product Owner has joined an existing Scrum Team that has been working together for eight Sprints.
The Development Team has grown to have a good understanding of the functionality and business for the product they have been building. The Product Owner, being new to the company, is unsure about his responsibilities.
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)

  • A. You tell the Product Owner to make sure that there are no ambiguities or possible misunderstandings in the items on the Product Backlog when they are handed over to the Development Team. This is best done by capturing the functional requirements during an analysis phase, resulting in documents that are considered as the working product of such analysis Sprints.
  • B. You advise the Product Owner to start building a good relationship with the stakeholders of the product.
    Ongoing interaction with them is important to regularly align with changing organizational or market expectations. The Product Owner is also expected to invite the right stakeholders to the Sprint Review meeting.
  • C. You inform the Product Owner that, in today's highly competitive markets, it is important that the Development Team is updated on changing business priorities on a daily basis. The Daily Scrum allows the Development Team to adapt to the changes in scope without delay.
  • D. You advise the Product Owner to rely on the Development Team and the stakeholders to formulate the Product Backlog, as they are the ones most knowledgeable. By asking questions and working with them the Product Owner will quickly be up to speed.

Answer: B,D

Explanation:
The ones that are closest to the work are the best ones to understand and explain what the work is and what the needs of the users and product are.

 

NEW QUESTION 56
Which statement best describes Scrum?

  • A. A clearly defined methodology that defines the software development process.
  • B. A framework to address complex products in complex environments.
  • C. A manual for defining best practices for software development.
  • D. A clearly defined and predictable process that follows the principles of Computer Science.

Answer: B

Explanation:
Frameworks allow those closest to the problem the flexibility to creatively and productively deliver products of the highest possible value. Each component of Scrum serves a specific purpose and is essential to Scrum's success and your usage of Scrum to develop complex projects.

 

NEW QUESTION 57
Your organization requires all Increments to pass user acceptance testing (UAT) before it is allowed to be released to production.
Is it a good idea to postpone UAT until the end of the project to prevent the Development Team from being disrupted during the Sprints?

  • A. Yes, because UAT is done in a hardening Sprint before the release Sprint.
  • B. It depends on the team's Definition of Done.
  • C. Yes, because the Development Team is a self-organizing team and should not be disrupted during development.
  • D. No, because the state of the Product Increment won't be transparent and the feedback loop would be too long.

Answer: D

Explanation:
The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the Scrum Team's current definition of "Done". At the end of a Sprint, the new Increment must be "Done", which means it must be in useable condition and meet the Scrum Team's definition of "Done". An increment is a body of inspectable, done work that supports empiricism at the end of the Sprint. If UAT is a part of the team or organizational standard, then any delay in this activity will reduce transparency and increase risk.

 

NEW QUESTION 58
Who must ensure that the work done for a Product Backlog item conforms to the Definition of "Done?"

  • A. The Development Team.
  • B. The Product Owner.
  • C. The test team.
  • D. The Scrum Team.
  • E. The Scrum Master.

Answer: A

Explanation:
Explanation/Reference:
Explanation:
The Development Team owns the Definition of "Done" and is accountable for the quality of the Product Backlog items.

 

NEW QUESTION 59
The Sprint length should be:

  • A. Short enough to keep the business risk acceptable to the Product Owner.
  • B. All of these answers are correct.
  • C. Short enough to be able to synchronize the development work with other business events.
  • D. No more than one month.

Answer: B

 

NEW QUESTION 60
Steven, a Scrum Master, is approached by the Development Team members complaining that one of the senior engineers is using too much time during the Daily Scrums to share technical solutions.
Which are the best two actions for Steven to take? (Choose two.)

  • A. Suggest that the team members timebox the amount of time each person can speak at the Daily Scrum to a maximum of two minutes.
  • B. Contact the team member's direct manager and to resolve this problem.
  • C. Speak with the person privately and coach him on the purpose of the Daily Scrum.
  • D. Coach the Development Team to help them find a way to solve the problem, and for them to take ownership of the solution.
  • E. Suggest using a token to limit who is allowed to speak during the Daily Scrum.

Answer: C,D

Explanation:
The Scrum Master serves the Development Team in several ways, including: Coaching the Development Team in self-organization and cross-functionality; Facilitating Scrum events as requested or needed.
It is the Scrum Master's responsibility to teach the Scrum Team the value and objective of each Scrum event in order to help them maximize the benefits of each event in accordance to the Scrum values and theory.

 

NEW QUESTION 61
Steven is a Scrum Master of a Development Team that has members working in different cities and time zones. Organizing the Scrum events is time consuming and requires a lot of effort to set up and run. The Development Team proposes to only hold the Daily Scrum on Mondays.
Which two responses would be most appropriate from Steven? (Choose two.)

  • A. Coach the team on why having a Daily Scrum every day is an important opportunity to update the Sprint plan and how it helps the team self-organize work toward achieving the Sprint Goal.
  • B. Acknowledge and support their decision.
  • C. Ensure that there is an overall consensus by having the Development Team members vote.
  • D. Help the Development Team understand that lowering the frequency of communication will only increase the feeling of disconnect between the team members.

Answer: A,D

Explanation:
The Scrum Master is responsible for ensuring that the Scrum Team understands the purpose and value of the Scrum events. Because the Daily Scrum is owned by the Development Team, it will decide how best to run the event. And if needed the Scrum Master will coach the team to ensure the decisions stay within the boundaries of the Scrum framework.

 

NEW QUESTION 62
Which approach would you recommend to ensure that the Product Backlog items discussed at Sprint Planning are well understood, actionable, and easier to forecast?

  • A. Having the Product Owner work with stakeholders between the end of the last Sprint and before beginning the next to prepare the Product Backlog items so not to interrupt the Development Team.
  • B. Having a separate group of business analysts and functional testers analyzing high-ordered Product Backlog items before Sprint Planning.
  • C. Having the business analysts in the Development Team create the upcoming Product Backlog items during a Sprint and adding them to the next Sprint's forecast.
  • D. Having the Development Team use some time during each Sprint to help the Product Owner analyze, estimate, and design items at the top of the Product Backlog that is projected to be worked on in the upcoming Sprint.

Answer: D

Explanation:
Product Backlog refinement is the act of adding detail, estimates, and order to items in the Product Backlog. This is an ongoing process in which the Product Owner and the Development Team collaborate on the details of Product Backlog items. During Product Backlog refinement, items are reviewed and revised. The Scrum Team decides how and when refinement is done. Refinement usually consumes no more than 10% of the capacity of the Development Team. However, Product Backlog items can be updated at any time by the Product Owner or at the Product Owner's discretion.

 

NEW QUESTION 63
Which of the following are time-boxed events in Scrum?

  • A. Daily Scrum
  • B. All of the above
  • C. Sprint Planning
  • D. Sprint Review
  • E. Sprint Retrospective

Answer: B

 

NEW QUESTION 64
What is the Development Team responsible for?

  • A. Writing User Stories and ordering the Product Backlog.
  • B. Organizing the work required to meet the Sprint Goal and resolving internal team conflicts.
  • C. Reporting productivity and selecting the Sprint time-box.

Answer: B

 

NEW QUESTION 65
Which of the following are feedback loops in Scrum?

  • A. Grooming, Daily Status, and Sprint Review
  • B. Daily Scrum, Sprint Review, and Sprint Retrospective
  • C. Release Planning, Daily Scrum, and Sprint Review
  • D. Daily Standup, Sprint Review, and Sprint Retrospective

Answer: B

 

NEW QUESTION 66
Your company has notified the stakeholders that they will be delivering the first release of a new product within ten Sprints. On the seventh Sprint, the Scrum Team discovers that they will not be able to include all of the expected features within the first release. The Product Owner believes if they remove some items from the Definition of Done they will be able to accelerate the development process. The Development Team objects to this idea as it will lead to technical debt.
As a Scrum Master, what would be the best two ways to explain to the Product Owner the impact of technical debt? (Choose two.)

  • A. The amount of technical debt will need to be analyzed in order to understand the impact on subsequent releases in order to allocate additional Sprints at the end of the project.
  • B. Reducing the Definition of Done will introduce unknown errors as development progresses and functionality is added. The system can become more difficult to stabilize as work progresses. Development for the actual release as well as future releases will be slowed down in unpredictable ways.
  • C. As long as there is still technical debt in the current release, feature development for the next release cannot be started. The Product Owner must first agree to this impact before allowing changes to the Definition of Done.
  • D. Releasing the version upon a reduced Definition of Done creates false assumptions about the actual state of the system. This will create many interruptions during the development of the next release as fixes will need to be done to the previous release caused from a reduction of quality.

Answer: B,D

Explanation:
The Definition of Done helps the Scrum Team have a shared understanding of what it means for work to be complete, to ensure transparency. The Definition of Done is used to assess when work is complete on the product Increment. It also ensures that the work that is done is in usable condition and meets the Development Teams quality standards for future sustainability.

 

NEW QUESTION 67
Which two scenarios would best represent a self-organizing Development Team? (Choose two.)

  • A. The Development Team creates its own Sprint Backlog, reflecting all work that is part of the Definition of Done.
  • B. The Development Team invites external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog.
  • C. Development Team members collaboratively select and re-plan their work throughout the Sprint.
  • D. Management works with the Scrum Master to optimize the Development Team's progress during the Sprint.
  • E. The Development Team members are strictly focused on the work within their functional role and always handing off the work to other roles in a timely matter.

Answer: A,C

Explanation:
A self-organized team is a team that is able to self-manage and decide how best to accomplish their work.

 

NEW QUESTION 68
You have a Scrum Team that has been working together for over a year. The Development Team consists of eleven members who rarely collaborate and work within their functional boundaries. There are no Sprint Goals and most of the items in the Sprint Backlog are unrelated. The Scrum Team has concluded that it is not possible to create Sprint Goals based on the items in the Product Backlog.
What might explain why the Scrum Team is finding it difficult to craft Sprint Goals? (Choose all that apply.)

  • A. Scrum might not be the best framework for this team.
  • B. The Sprints are too long.
  • C. The Product Owner is not empowered to make decisions about items in the Product Backlog nor how they are ordered.
  • D. The Product Owner doesn't set objectives that he/she wants to achieve with upcoming Sprints.
  • E. The Development Team is too big.

Answer: A,C,D

Explanation:
Many people misinterpret the Scrum Guide as stating the Development Team size is limited to 3-9 members. In reality, it only states that there is inherent risk attached to having less than 3 members and more than 9 members. As the number of members increases, the lines of communication also increase. This can be calculated using the Group intercommunication formula: n(n − 1) / 2 where n is the number of members. Some teams are able to handle the risk and "synergize" whereas others might struggle. Saying that, the relationship between defining a Sprint Goal and Development Team size is unclear.
But the relationship between the ordering of the Product Backlog, the PO having clear objectives, and the Sprint Goal are direct. The Product Owner typically comes to the Sprint Planning with a business objective in mind and Product Backlog items related to the business objective. After deciding what can be done for the upcoming Sprint, the Scrum Team will craft a Sprint Goal that would be met through the implementation of the items. This is not dependent on the size of the team nor length of the Sprint.
Scrum is also a framework that's fit for purpose. Some projects/products are not fit for Scrum... or, better stated, Scrum is not suitable for all projects/products.

 

NEW QUESTION 69
......