The Open Group Certification Real Exam Questions and Answers FREE OG0-093 Updated on Dec 16, 2021 [Q215-Q233]

Share

The Open Group Certification OG0-093 Real Exam Questions and Answers FREE Updated on Dec 16, 2021

OG0-093 Ultimate Study Guide -  ActualCollection


2. 0G0-092 Exam

There are 8 topics that the candidates need to learn. They include the following:

  • ADM Phases. This is divided into three subsections: Establishment of Projects, Definition of Architecture, and Governance. The areas that are captured include preliminary phase, architecture vision, business architecture, architecture for information systems, data architecture, application architecture, and technology architecture. Besides that, you should know about opportunities and solutions, migration planning, implementation planning, change management for architecture, and requirements management for ADM architecture.
  • ADM Adaptation. This domain is all about levels, iteration, and security. It covers iteration concepts, factors that influence iteration usage, iteration cycles, architecture for enterprise security, adapting ADM security, and more.
  • Architecture Content Framework. This one covers TOGAF ADM and content framework, Metamodel, Content Metamodel, and the core concepts of Metamodel.
  • Enterprise Continuum. As for this topic, it touches on architecture partitioning, which includes classifying partitioned architectures and partitioning ADM. Also, you should learn about the architecture repository with the knowledge areas, such as architecture model, architecture landscape, reference library, governance log, solutions landscape, enterprise repository, architecture capability, and so on.
  • Reference Models for TOGAF. This area includes TOGAF Technical Reference Models (TRM), TRM structure, and Integrated Information Infrastructure Reference Model (III-RM).
  • Capability Framework for Architecture. Within this section, it is required to know about various technical areas, such as architecture governance, maturity models for architecture, and skills framework for architecture.

 

NEW QUESTION 215
Complete the sentence. The Requirements Management process is used to______.

  • A. dispose of, address and prioritize architecture requirements
  • B. review business requirements
  • C. validate requirements between ADM phases
  • D. organize architecture requirements throughout the ADM cycle
  • E. develop requirements for Transition Architectures that deliver business value

Answer: D

 

NEW QUESTION 216
Complete the sentence. In a gap analysis, a building block that appears in the Target Architecture but does not appear in the Baseline Architecture indicates _____

  • A. requirements have not been properly documented
  • B. functionality that should be eliminated
  • C. a new function that must be built or procured
  • D. an error has occurred and the architecture must be re-evaluated
  • E. nonconformant solution building blocks

Answer: C

Explanation:
Section: Part 2

 

NEW QUESTION 217
Which of the following statements about TOGAF Building Blocks and their use in the ADM cycle is correct?

  • A. Building Blocks become more implementation-specific in Phase E
  • B. Building Blocks in phases D, E and F are evolved to a common pattern of steps
  • C. Building Blocks should be identified in abstract form as part of the Preliminary Phase
  • D. Building Blocks should be first selected in Phase D

Answer: A

Explanation:
Section: Part 1
Explanation/Reference:

 

NEW QUESTION 218
Which one of the following best describes the Architecture Vision document?

  • A. A set of rules and guidelines to support fulfilling the mission of the organization
  • B. A set of quantitative statements outlining requirements on the implementation
  • C. A description of how the new capability will address stakeholder concerns
  • D. An agreement between development partners and the sponsor on architecture deliverables
  • E. A description of the scope and approach for completion of the architecture project

Answer: C

 

NEW QUESTION 219
Which of the following does TOGAF describe as "the structure of components, their inter-relationships, and the principles guiding their design and evolution over time"?

  • A. Artifact
  • B. View
  • C. Architecture
  • D. Deliverable
  • E. Model

Answer: C

 

NEW QUESTION 220
Scenario
Please read this scenario prior to answering the Question
You are working as a consultant to the Chief Architect at a government agency responsible for securing all government communications and information systems. The agency has recently received funding for a program that will upgrade the reliability and performance of its secure communication systems which provide real-time, highly secure communication of voice, video, and message data to remote locations around the world.
The agency has an established enterprise architecture (EA) capability based on TOGAF 9. The Executive Director of the agency is the sponsor of the EA capability.
Since reliable, high-performance, and secure communications are essential to preserving national security, the Executive Director has placed more stringent requirements for the architecture for the upgraded system. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow more stringent requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.
A portion of the program budget has been allocated to context a review of the EA. The scope of the review is to evaluate the processes, content and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.
The Chief Architecture has noted that the core EA artifacts that have been used since TOGAF 9 was introduced are not adequate to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implementations that match some of the new requirements, but they are only used in a few areas.
Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.
Refer to the Scenario
You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.
Based on TOGAF, which of the following is the best answer?

  • A. Since this case requires extensions of the modeling and data details of the service, this is best done by using the services extension of the TOGAF 9 Content Metamodel. By using this extension, the service model is no longer constrained by what is expected in typical business service definitions, allowing more flexibility for adding customized models to support the more stringent measurement requirements. The services extension can also be used to map terminology between the business services and the application components.
  • B. You recommend all of the TOGAF 9 Content Metamodel extensions be incorporated into the Architecture Content Metamodel. The full Content Metamodel will enable the EA team to capture and categorize all the important additional data needs to support the performance and measurement objectives linked to these artifacts. Once the new repository content has been implemented, on- demand queries can be used to generate a customized governance stakeholder view that isolates the artifacts and data needed to assess measurement for any particular service. If this view is found to be inadequate for the governance concerns, the service models within those artifacts can be expanded.
  • C. To support the type of stringent performance measurements needed for the more detailed governance views required for the upgraded system, the interfaces to the communication and network layer of the architecture must be highly visible at the application level. To accommodate the proper development of this, a Communications Engineering view should be created from the infrastructure extension models of the TOGAF Content Metamodel. This view will allow architects to align the required performance measurement communications across the system.
  • D. Since some artifacts will now require specific measurements and additional data will be needed to support the performance objectives linked to these measurements, you recommend that the motivation and governance extensions of the TOGAF 9 Content Metamodel are used. Using these extensions will allow modeling the goals, objectives and drivers for the architecture, linking them to service levels and more detailed governance models. This will also enable the ability to re-use existing profiles, customizing them for the various service contracts involved.

Answer: A

Explanation:
Section: Part 2
Explanation/Reference:

 

NEW QUESTION 221
Scenario:
Please read this scenario prior to answering the question
Your role is that of Lead Enterprise Architect working at the headquarters of a fast food chain. The chain manages over 7500 restaurants across 33 countries. Each restaurant in the chain is an independently owned and operated franchise.
Many of the restaurants still use the first generation IT systems deployed over 10 years ago. The Chief Operating Officer (COO) of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business including providing its franchisees new support services to help them address the increasing competition from coffee shops. This is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
The changes will help provide the chain with improved products, including healthier alternatives in the menu, and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions.
The chain has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the COO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.
Based on the recommendation from the initial study, the decision has been taken for the chain to adopt a packaged suite of integrated application that is tailored to the needs of the franchise.
Refer to the scenario.
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the COO's vision.
Based on the TOGAF standard, Version 9.2, which of the following is the best answer?

  • A. You propose that the target architecture is defined first by going through the architecture definition phases (B-D). This is because the initial study identified the need to change. This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.
  • B. You propose that the target architecture is defined first, followed by transition planning. This is because the vision is well understood and the strategic architecture agreed. The target first approach will ensure that the current problems and inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial study.
  • C. You propose that the baseline Technology Architecture is defined first in order to assess current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
  • D. You propose that the focus be placed on architecture definition, with emphasis on understanding the strategic change parameters. The requirements, drivers, issues and constraints for this engagement can then be identified. You would ensure that the target architecture addresses not functional requirements so as to ensure the target architecture is robust and secure.

Answer: A

Explanation:
Section: Part 2

 

NEW QUESTION 222
Which one of the following describes a purpose of an Architecture Compliance review?

  • A. To evaluate the readiness of the organization to undergo change
  • B. To produce a new Request for Architecture Work
  • C. To define the capabilities of the organization
  • D. To communicate the technical readiness of the project

Answer: D

Explanation:
Section: Part 2

 

NEW QUESTION 223
Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Sollace Manufacturing Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project.
One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
[Note: You should assume that Sollace Manufacturing has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] Based on TOGAF 9, which of the following is the best answer?

  • A. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data Security
  • B. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management
  • C. Business Continuity, Service-orientation, Data is Accessible, Data Security, Responsive Change Management
  • D. Common-use Applications, Data is Shared, Data is Accessible, Data Security, Interoperability, Control Technical Diversity

Answer: B

 

NEW QUESTION 224
In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

  • A. Phase A
  • B. Phase G
  • C. Phase H
  • D. Phase F
  • E. Phase E

Answer: D

Explanation:
Section: Part 2
Explanation/Reference:
Reference https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap14.html

 

NEW QUESTION 225
Which of the following is described by the TOGAF document as "a detailed plan of the system at component level to guide its implementation"?

  • A. Artifact
  • B. View
  • C. Architecture
  • D. Deliverable
  • E. Model

Answer: C

 

NEW QUESTION 226
What part of the Architecture Repository holds specifications to which architectures must conform?

  • A. Enterprise Continuum
  • B. Governance Log
  • C. Architecture Landscape
  • D. Standards Information Base
  • E. Reference Library

Answer: D

 

NEW QUESTION 227
Which of the following best describes an architectural change categorized as a re-architecting change?

  • A. A change to re-align with the business strategy
  • B. A change to derive additional value from the existing investment
  • C. A change to reduce costs
  • D. A change to increase investment in order to create new value for exploitation

Answer: D

Explanation:
Explanation/Reference:
Reference: http://pubs.opengroup.org/architecture/togaf8-doc/arch/chap14.html

 

NEW QUESTION 228
Which of the following describes a purpose of an Architecture Compliance review?

  • A. Identifying business transformation risks for an architecture project
  • B. Identifying stakeholders and their concerns
  • C. Identifying where standards may require modification
  • D. Identifying relationships between management frameworks

Answer: C

Explanation:
Explanation
Reference
http://pubs.opengroup.org/architecture/togaf8-doc/arch/chap24.html

 

NEW QUESTION 229
According to TOGAF, which of the following best describes the purpose of an Architecture Roadmap?

  • A. To show progression of change from the Baseline Architecture to the Target Architecture
  • B. To ensure that architecture information is communicated to the right stakeholders at the right time
  • C. To act as a deliverable container for artifacts created during a project
  • D. To provide a high-level view of the end architecture product
  • E. To govern the architecture throughout its implementation process

Answer: A

 

NEW QUESTION 230
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been
growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters
and the business units has increasingly caused problems in the handling of customer and financial
information. The inability to share information across businesses has resulted in lost opportunities to
"leverage the synergies" that had been intended when the businesses were acquired. At present, each
business unit maintains its own applications. Despite an earlier initiative to install a common application to
manage customer, products, supplier, and inventory information, each business unit has different ways of
defining each of these core elements and has customized the common application to the point where the
ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to
consolidate information from several applications that exist across the lines of business. The application
will be used by all business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard
confidential customer information in a secure manner that meets or exceeds the legal requirements of the
countries in which the company operates. This will be an increasingly important capability as the company
expands its online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is
to coordinate efforts between the implementation team and the business unit personnel who will be
involved in the migration process. The CIO has also formed a cross-functional Architecture Board to
oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this
choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the
appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

  • A. You evaluate the implications of the Board's concerns by examining the security and regulatory
    impacts on business goals, business drivers and objectives. Based on your understanding, you then
    update the current security policy to include an emphasis on the concerns. You define architecture
    principles to form constraints on the architecture work to be undertaken in the project. You then
    allocate a security architect to ensure that security considerations are included in the architecture
    planning for all domains.
  • B. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory
    requirements and their impact on business goals and objectives. Based on this understanding, you
    then issue a Request for Architecture Work to commence an architecture development project to
    develop a solution that will address the concerns. You allocate a security architect to oversee the
    implementation of the new application that is being developed.
  • C. You identify and document the security and regulatory requirements for the application and the data
    being collected. You ensure that written policies are put in place to address the requirements, and that
    they are communicated across the organization, together with appropriate training for key employees.
    You identify constraints on the architecture and communicate those to the architecture team. You
    establish an agreement with the security architects defining their role within the ongoing architecture
    project.
  • D. You start by clarifying the intent that the Board has for raising these concerns. This enables you to
    understand the implications of the concern in terms of regulatory requirements and the potential impact
    on current business goals and objectives. You propose that a security architect or security architecture
    team be allocated to develop a comprehensive security architecture and that this be considered an
    additional domain architecture.

Answer: A

Explanation:
Explanation/Reference:
Incorrect:
Not C: Implied that solution needs be developed to address the concern, instead of address the concern in
the ERP solution itself.

 

NEW QUESTION 231
According to TOGAF, which of the following best describes the classification of architectural change in the
case where multiple server systems are being consolidated to a single system?

  • A. A simplification change handled via change management techniques
  • B. A re-architecting change that puts the whole architecture through an ADM cycle
  • C. A bottom-up change to enhance operational capability
  • D. A revision change of the enterprise architecture
  • E. An incremental change handled via change management techniques

Answer: A

 

NEW QUESTION 232
Which section of the TOGAF template for Architecture Principles should clearly state the impact to the business and consequences of adopting the principle?

  • A. Rationale
  • B. Name
  • C. Implications
  • D. Statement

Answer: C

Explanation:
Topic 2, Part 2

 

NEW QUESTION 233
......

Ultimate Guide to Prepare OG0-093 Certification Exam for The Open Group Certification: https://www.actualcollection.com/OG0-093-exam-questions.html

Use Real OG0-093 Dumps - The Open Group Correct Answers: https://drive.google.com/open?id=138zdNNv6o9JelwjH7nmjuKnU8PxhihLs