Online test engine bring you new experience
When you download and install online test engine in your computer, it allows you to take practice Oracle EBS R12: Advanced Supply Chain Planning actual questions by fully simulating interactive exam environment. You can install in your Smartphone because online version supports any electronic equipment. When you do Oracle EBS R12: Advanced Supply Chain Planning actual collection, you can set your time and know well your shortcoming. Besides, you can review your 1Z0-244 - Oracle EBS R12: Advanced Supply Chain Planning actual exam dumps anywhere and anytime. According to the comments from our candidates, such simulation format has been proven to the best way to learn, since our study materials contain valid Oracle EBS R12: Advanced Supply Chain Planning actual questions.
The aim of ActualCollection is help every candidates getting certification easily and quickly. Comparing to attending expensive training institution, ActualCollection is more suitable for people who are eager to passing Oracle EBS R12: Advanced Supply Chain Planning actual test but no time and energy. If you decide to join us, you will receive valid Oracle EBS R12: Advanced Supply Chain Planning actual exam dumps with real questions and detailed explanations. We promise you if you failed the exam with our 1Z0-244 - Oracle EBS R12: Advanced Supply Chain Planning actual collection, we will full refund or you can free replace to other dumps. If you have any questions, please feel free to contact us and we offer 24/7 customer assisting to support you.
For most office workers, it is really a tough work to getting Oracle EBS R12: Advanced Supply Chain Planning certification in their spare time because preparing Oracle EBS R12: Advanced Supply Chain Planning actual exam dumps needs plenty time and energy. As the one of certification of Oracle, Oracle EBS R12: Advanced Supply Chain Planning enjoys a high popularity for its profession and difficulty. With Oracle EBS R12: Advanced Supply Chain Planning certification you will stand out from other people and work with extraordinary people in international companies. The matter now is how to pass the Oracle EBS R12: Advanced Supply Chain Planning actual test quickly. Maybe you can get help from ActualCollection. You just need to spend your spare time to practice the 1Z0-244 actual questions and Oracle EBS R12: Advanced Supply Chain Planning actual collection, and you will find passing test is easy for you.
ActualCollection is a website engaged in the providing customer Oracle EBS R12: Advanced Supply Chain Planning actual exam dumps and makes sure every candidates passing Oracle EBS R12: Advanced Supply Chain Planning actual test easily and quickly. We have a team of IT workers who have rich experience in the study of Oracle EBS R12: Advanced Supply Chain Planning actual collection and they check the updating of Oracle EBS R12: Advanced Supply Chain Planning actual questions everyday to ensure the accuracy of 1Z0-244 - Oracle EBS R12: Advanced Supply Chain Planning exam collection. You can free download the trial of Oracle EBS R12: Advanced Supply Chain Planning actual collection before you buy. Besides, you have access to free update the Oracle EBS R12: Advanced Supply Chain Planning actual exam dumps one-year after you become a member of ActualCollection.
Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
1. In a combination of forecasts for one Item, the Planning Manager consumes forecast entries according to the following procedural list:
1. It consumes the entries on the sales order line schedule date (or within the same week or period).
2. It consumes the entries on the forward consumption days (or within the same week or period).
3. It consumes the entries on the backward consumption days (or within the same week or period).
Note: No other setups are performed for consumption. Identify the correct order of consumption.
A) 3, 2, 1
B) 2, 3, 1
C) 1, 2, 3
D) 3, 1, 2
E) 1, 3, 2
F) 2, 1, 3
2. Company ABC ran an ASCP plan with the Enforce Capacity Constraints Constrained option.
The planning Input Is: Sales Order Item: XYZ001
Sales Order Due date: 15 March Sales Order quantity: 1000
The supplies pegged to this sales order line are:
Job 1: Quantity 500 and due date 13 March Job
2: Quantity 200 and due date 15 March Job
3: Quantity 300 and due date 17 March
Which three statements are true in the above example about the Sales Order Due date?
A) Quantity satisfied by Sales Order line schedule date is 700.
B) Days Late is 2 (17 March - 15 March).
C) Days Late is 4 (17 March - 13 March).
D) Days Late Is 2 (15 March - 13 March).
E) Demand is satisfied onl5 March.
F) Demand is satisfied onl7 March.
3. Your client Is set up to run a Constrained plan ABC. This plan Is set up with the Enforce Demand Due Dates option.
The plan ABC Is run successfully and the outcome of the plan is ready.
Which three options can be expected as recommendations out of the plan ABC run?
A) One machine resource Is overloaded.
B) Planning time fence is respected.
C) A purchase requisition Is scheduled within the lead-time set for the Item.
D) One of the demands is going to be fulfilled late.
E) A Job is scheduled to use two resource units when there is only one resource unit available.
4. The MSO:Enable Decision Rules profile option is set to "No." Then a Constrained but not Optimized plan Is run.
Identify three statements that are true.
A) Substitute items will be considered.
B) Alternate BOMs will not be considered.
C) Default Demand priorities will be considered in the order of Sales Order, Forecast, and Safety Stock.
D) Alternate Routings will not be considered.
E) Alternate BOMs will be considered.
5. Identify the three correct statements about the setups required to enable pegging within an ASCP plan.
A) Set the MSO: Firm Supply Allocation Window (Backward days) System Profile to the number of days to search backward from the Demand Date. The allocation of firm supplies is based on demand priorities within the Firm Supply Allocation window.
B) In plan options, if you use the Enable Pegging check box to enable pegging, the Planned Items field determines the Items for which pegging will be calculated.
C) Set the MSO: Firm Supply Allocation Window (Forward days) System Profile to the number of days to push any supply order forward to complete a Work Order, even if there is some excess. This ensures that the supply is not pegged to a Safety Stock.
D) Setting the MSC: Use FIFO Pegging profile option to "Yes" pegs high-priority demands first to on- hand and firm supplies, and then continues with other existing and nonfirm supplies.
E) To enable pegging for an Item, you must set the Pegging Item Attribute to any value except
-None."
F) To enable Priority Pegging, select the Peg Supplies by Demand Priority check box In the plan options.
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: A,D,F | Question # 3 Answer: A,C,E | Question # 4 Answer: C | Question # 5 Answer: C,E,F |